Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: FIRE - FINAL
Permit Number - T17CM04612
Inspection Description - FIRE - FINAL
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/25/2019 | FIRE - FINAL | Approved | ||
| 07/11/2019 | FIRE - FINAL | Partial Approval | Updated Punch List for Buildings 1 and 3 -Install caps on all standpipes -Need Red Lock Outs and Labels for Fire Alarm -Access Control -Mag Locks need to be tested -Bldg 3 Package Room missing smoke seal -Bldg 3 3402 needs permanent addressing -Bldg 3 3403 needs smoke seal -Bldg 3 Level 1 North Mechanical Room Painted Sprinkler Head -As builts and owners manual needed onsite -Service contract w/ NFPA 72 form |
|
| 07/09/2019 | FIRE - FINAL | Partial Approval | Tested Fire Alarm devices for Buildings 1 and 3. Punch list was created for contractor. Follow up inspection on Thursday 7/11/19 is scheduled. | |
| 06/26/2019 | FIRE - FINAL | Partial Approval | Walked Buildings 1 and 3. Tested Interlocked Smoke Detectors, Smoke Seals, Door Closures and Room Numbering. Punch list was created with contractor. | |
| 06/18/2019 | FIRE - FINAL | Partial Approval | Ok for TCO to move in furniture and stock supplies for Building 2. | |
| 06/11/2019 | FIRE - FINAL | Partial Approval | Ok for TCO to move in furniture and stock supplies for Building 1. | |
| 06/04/2019 | FIRE - FINAL | Partial Approval | OK for TCO to move in furniture and stock supplies for Building 3. | |
| 05/14/2019 | FIRE - FINAL | Partial Approval | Tested the fire pump. The fire pump passed the inspection, however, the signals could not be verifyed to the fire alarm system so the fire pump is locked out until the signals can be confirmed. Need to verify that the fire pump, water flow and tamper signals are reportting off site prior to approving a TCO for fixturing of the building. |