Permit: T17CM04612

Parcel: 124071390


Addresses:

55 N PARK AV BLDG#1

Inspection Status: Approved

Inspection History: MECHANICAL - INTERMEDIATE

Date Description Inspector Results Comments
07/23/2019 MECHANICAL - INTERMEDIATE Approved
03/27/2019 MECHANICAL - INTERMEDIATE Partial Approval Maintenance restroom in basement OK to cover interior walls. Plumbing re-vent on north wall needs continuous grade for gravity venting.
03/15/2019 MECHANICAL - INTERMEDIATE Not ready for Inspection Registers not in place
03/11/2019 MECHANICAL - INTERMEDIATE Partial Approval Building #2, Level #8, Room #2802. Ok to cover walls.
03/08/2019 MECHANICAL - INTERMEDIATE Not ready for Inspection contractor cancelled
03/05/2019 MECHANICAL - INTERMEDIATE Not ready for Inspection Contractor cancelled.
03/04/2019 MECHANICAL - INTERMEDIATE Partial Approval study room, bathrooms, bicycle storage. Ok to cover walls.
02/28/2019 MECHANICAL - INTERMEDIATE Not ready for Inspection Contractor cancelled.
02/25/2019 MECHANICAL - INTERMEDIATE Not ready for Inspection Contractor cancelled.
02/21/2019 MECHANICAL - INTERMEDIATE Not ready for Inspection Contractor cancelled.
02/20/2019 MECHANICAL - INTERMEDIATE Partial Approval Building #2, Level #8, Rooms 2808-2816. Ok to cover walls.
02/19/2019 MECHANICAL - INTERMEDIATE Partial Approval Units 2806, 2807, 2808 on the eighth floor OK to drywall.
Unit 2602 sixth floor OK to drywall.
02/15/2019 MECHANICAL - INTERMEDIATE Cancelled canceled by the contractor.
02/11/2019 MECHANICAL - INTERMEDIATE Partial Approval Building #2, Level #8; Rooms 2803, 2804, 2805.
02/08/2019 MECHANICAL - INTERMEDIATE Not ready for Inspection Contractor cancelled.
02/05/2019 MECHANICAL - INTERMEDIATE Partial Approval Building #2, Level #5, Room 2502. Ok to Sheetrock
02/01/2019 MECHANICAL - INTERMEDIATE Partial Approval Building #2; Level #7; Rooms 2706 - 2708. Ok to insulate and sheetrock.
01/31/2019 MECHANICAL - INTERMEDIATE Partial Approval Building #2, Level #7, Rooms 2703-2705. Ok to cover walls.
01/30/2019 MECHANICAL - INTERMEDIATE Not ready for Inspection Contractor cancelled
01/25/2019 MECHANICAL - INTERMEDIATE Partial Approval Building #2, Level #7. Rooms 2711, 2712, 2713. Ok to Sheetrock progress areas.
01/24/2019 MECHANICAL - INTERMEDIATE Partial Approval Building #2, Level #7; Rooms: 2715 2716, 2718. Ok to sheetrock
01/22/2019 MECHANICAL - INTERMEDIATE Partial Approval Building #2, Level #6, Rooms 2611, 2612. Ok to insulate and Sheetrock.
01/17/2019 MECHANICAL - INTERMEDIATE Partial Approval Building #1, Level #4 Rooms 1403, 1404, 1405, 1406. Ok to insulate and Sheetrock.
01/16/2019 MECHANICAL - INTERMEDIATE Partial Approval Building #1, Level #4, Rooms 1401, 1402, 1407, 1408. Building #2, Level #4, Room #2402 and corridors
01/11/2019 MECHANICAL - INTERMEDIATE Not ready for Inspection Contractor cancelled.
01/08/2019 MECHANICAL - INTERMEDIATE Partial Approval Building #1, Level #3, Rooms and corridors. Ok to cover walls
01/07/2019 MECHANICAL - INTERMEDIATE Partial Approval Building #2, Level #6; Rooms 2603, 2604, 2605
01/04/2019 MECHANICAL - INTERMEDIATE Cancelled All intermediate inspections canceled by contractor
01/02/2019 MECHANICAL - INTERMEDIATE Not ready for Inspection contractor cancelled
12/28/2018 MECHANICAL - INTERMEDIATE Partial Approval Building #2, Level #6; Rooms #2606 - 2607; 2613 - 2618. Ok
to insulate and cover walls
12/20/2018 MECHANICAL - INTERMEDIATE Partial Approval Building #1; lLevel #2; Rooms 1201-1208
12/19/2018 MECHANICAL - INTERMEDIATE Partial Approval Building #2, Level #5, Rooms #2501 - 2507
12/12/2018 MECHANICAL - INTERMEDIATE Partial Approval Building #2, Level 5 Rooms #2513-2528. Building #1. Level #1, all living rooms
12/06/2018 MECHANICAL - INTERMEDIATE Not ready for Inspection Contractor cancelled
11/29/2018 MECHANICAL - INTERMEDIATE Partial Approval Building #2, Level #4, Rooms: 2413-2418. Ok to cover walls.
11/19/2018 MECHANICAL - INTERMEDIATE Partial Approval Building # 2, Level #3, Rooms 2301-2303.
11/15/2018 MECHANICAL - INTERMEDIATE Partial Approval Building #2, Level #3, Rooms #2304 - 2307. Ok to cover walls and ceilings.
11/08/2018 MECHANICAL - INTERMEDIATE Partial Approval Building #2 Level 3, Units #2313 - 2318
11/02/2018 MECHANICAL - INTERMEDIATE Partial Approval Building #2, Level #2 North rooms, #2201-2207.
10/26/2018 MECHANICAL - INTERMEDIATE Not ready for Inspection Contractor cancelled
10/25/2018 MECHANICAL - INTERMEDIATE Partial Approval Unit 2 to13 through 2218 OK to cover