Permit: T17CM04612

Parcel: 124071390


Addresses:

55 N PARK AV BLDG#1

Inspection Status: Approved

Inspection History: ELECTRIC - INTERMEDIATE

Date Description Inspector Results Comments
07/23/2019 ELECTRIC - INTERMEDIATE Approved
03/27/2019 ELECTRIC - INTERMEDIATE Partial Approval Maintenance restroom in basement OK to cover interior walls. Plumbing re-vent on north wall needs continuous grade for gravity venting.
03/22/2019 ELECTRIC - INTERMEDIATE Partial Approval Building #2, Level #6 Amenities area, in walls and above ceiling. Ok to cove
03/15/2019 ELECTRIC - INTERMEDIATE Partial Approval Amenities Building, Level #6. Walls and above ceiling in high area.
03/11/2019 ELECTRIC - INTERMEDIATE Partial Approval Building #2, Level #8, Room # 2802 Ok to cover walls.
03/08/2019 ELECTRIC - INTERMEDIATE Not ready for Inspection contractor cancelled
03/07/2019 ELECTRIC - INTERMEDIATE Partial Approval Building #2, Level #7: Meter sets, meters #2702, 2703, 2704, 2705, 2706, 2707, 2708, 2711, 2712, 2713, 2715, 2716, 2718. Ok to set meters
03/05/2019 ELECTRIC - INTERMEDIATE Not ready for Inspection Contractor cancelled.
03/04/2019 ELECTRIC - INTERMEDIATE Partial Approval Study room, bathrooms, bicycle storage. In wall electric.
03/01/2019 ELECTRIC - INTERMEDIATE Partial Approval Building #1, Level #1: meter sets, #1101, 1102, 1103, 1104, 1105, 1106, 1107, 1108; 1201, 1202, 1203, 1204, 1205, 1206, 1207, 1208, B1HP.
OK to set meters: CODE: CEC.
02/28/2019 ELECTRIC - INTERMEDIATE Partial Approval Clearance: Code: CECBuilding #2, Level #6, meter sets #2501, 2502, 2503, 2504, 2505, 2506, 2507, 2513, 2515, 2516, 2517, 2518, 2318; 2602: 2603, 2604, 2605, 2606, 2607, 2611, 2612, 2613, 2615. Ok to set meters.
02/25/2019 ELECTRIC - INTERMEDIATE Partial Approval Study room in wall electric.
02/22/2019 ELECTRIC - INTERMEDIATE Partial Approval Building #2, Level #4: Meter sets at meters #2301, 2302, 2303, 2304, 2305, 2306, 2307; 2313, 2314, 2315, 2316, 2317; 2401, 2402, 2403, 2404, 2405, 2406, 2407, 2413, 2414, 2415, 2416, 2417, 2418. Ok to set meters
02/21/2019 ELECTRIC - INTERMEDIATE Partial Approval Building #3, Level #4; meter set, ok to set meter #3401.
02/21/2019 ELECTRIC - INTERMEDIATE Partial Approval Building #4 Level #4 meter set #3401. Ok to set meter.
02/20/2019 ELECTRIC - INTERMEDIATE Partial Approval Building #2, Level #8, Rooms 2808-2816. Ok to cover walls.
02/19/2019 ELECTRIC - INTERMEDIATE Partial Approval Units 2806, 2807, 2808 on the eighth floor OK to drywall.
Unit 2602 sixth floor OK to drywall.
02/15/2019 ELECTRIC - INTERMEDIATE Cancelled canceled by the contractor.
02/14/2019 ELECTRIC - INTERMEDIATE Partial Approval Building #2; meter sets: #2101-2107; 2113-2118; 2201-2207, 2213-2218; B2HP, BPS2. Building #3; meter 3401.
02/11/2019 ELECTRIC - INTERMEDIATE Partial Approval Building #2, Level #8, Rooms 2803, 2804, 2805: remove wet and moldy insulation.
02/08/2019 ELECTRIC - INTERMEDIATE Not ready for Inspection Contractor cancelled
02/05/2019 ELECTRIC - INTERMEDIATE Partial Approval Building #2, Level #5, Room 2502. Ok to Sheetrock
02/04/2019 ELECTRIC - INTERMEDIATE Partial Approval Building #3: Meters 3102-3105, 3202-3205, B3Hp-2M HP,
3301-3305, 3401-3405, B3HP-1MHP
02/01/2019 ELECTRIC - INTERMEDIATE Partial Approval Building #3, Level #7; Rooms 2706-2708. Ok to insulate and sheetrock.
01/31/2019 ELECTRIC - INTERMEDIATE Partial Approval Building #2, Level #7, Rooms 2703-2705. Ok to cover walls.
01/30/2019 ELECTRIC - INTERMEDIATE Partial Approval Building #3 Meters: 3102-3105; 3202-3205; 3301-3305; 3401-3405; B3HP-2M, B3HP-1M
01/25/2019 ELECTRIC - INTERMEDIATE Partial Approval Building #2, Level #7, Rooms 2711, 2712, 2713. Ok to Sheetrock progress areas.
01/23/2019 ELECTRIC - INTERMEDIATE Partial Approval Building #2, Level #7; Rooms: 2715, 2716 2718. Ok to sheetrock.
01/22/2019 ELECTRIC - INTERMEDIATE Partial Approval Building #2, Level #6, Rooms: 2611, 2612. Ok to insulate and Sheetrock.
01/17/2019 ELECTRIC - INTERMEDIATE Partial Approval Building #1, Level #4, Rooms 1403, 1404, 1405, 1406. Ok to insulate Sheetrock
01/16/2019 ELECTRIC - INTERMEDIATE Partial Approval Building #1, Level #4; Rooms 1401, 1402, 1407, 1408. Building #2, Level #4; Room #2402 and corridors
01/11/2019 ELECTRIC - INTERMEDIATE Not ready for Inspection Contractor cancelled.
01/08/2019 ELECTRIC - INTERMEDIATE Partial Approval Building #1: Level #3: Rooms and corridors
01/07/2019 ELECTRIC - INTERMEDIATE Partial Approval Building #2. Level #6; Rooms : 2603, 2604, 2605
01/04/2019 ELECTRIC - INTERMEDIATE Cancelled All intermediate inspections canceled by contractor
01/02/2019 ELECTRIC - INTERMEDIATE Not ready for Inspection contractor cancelled
12/28/2018 ELECTRIC - INTERMEDIATE Partial Approval Building #2, Level #6; Rooms #2606 - 2607; 2613 - 2618. Ok to insulate and cover walls.
12/20/2018 ELECTRIC - INTERMEDIATE Partial Approval Building #1, Level #2: Rooms. 1201-1208
12/19/2018 ELECTRIC - INTERMEDIATE Partial Approval Building #2; Level #5, Rooms # 2501 - 2507
12/12/2018 ELECTRIC - INTERMEDIATE Partial Approval Building #2, Level 5 Rooms #2513-2518. Building #1, all living rooms. Ok to insulate and sheetrock.
12/10/2018 ELECTRIC - INTERMEDIATE Partial Approval Building #2, Level #4, Rooms #2401-2407
11/29/2018 ELECTRIC - INTERMEDIATE Partial Approval Building #2, Level #4, Rooms #2413-2418. Ok to cover walls.
11/19/2018 ELECTRIC - INTERMEDIATE Partial Approval Building #2, Level #3, Rooms #2301 - 2303
11/15/2018 ELECTRIC - INTERMEDIATE Partial Approval Building #2, Level #3. Rooms #2304 - 2307. Ok to cover walls and ceilings.
11/08/2018 ELECTRIC - INTERMEDIATE Partial Approval Building #2, Level 3, units #2313 - 2318.
11/02/2018 ELECTRIC - INTERMEDIATE Partial Approval Building #2, Level #2, North rooms #2201-2207.
10/26/2018 ELECTRIC - INTERMEDIATE Not ready for Inspection
10/25/2018 ELECTRIC - INTERMEDIATE Partial Approval Unit 2 to13 through 2218 OK to cover
10/24/2018 ELECTRIC - INTERMEDIATE Partial Approval Building #2, Level #9: conduits and boxes in place. Ok to cover.
10/17/2018 ELECTRIC - INTERMEDIATE Partial Approval Electric in walls, Building #2, Level #1, Rooms #2101 - 2107
10/12/2018 ELECTRIC - INTERMEDIATE Partial Approval Building #2, Level #1, South, Rooms #1113 - 1118
10/10/2018 ELECTRIC - INTERMEDIATE Partial Approval Building #2, Level #8; GL: N - Y/2 - 12. Conduits and boxes are in place. Ok to cover progress areas
10/01/2018 ELECTRIC - INTERMEDIATE Partial Approval Building #2. Level #9 West: GL: B-G/2-12, conduits and boxes are in place.
09/26/2018 ELECTRIC - INTERMEDIATE Partial Approval Garage, Level #7 slab, conduits and boxes are in place.
09/24/2018 ELECTRIC - INTERMEDIATE Partial Approval BUILDING #2, LEVEL #9 EAST, CONDUITS AND BOXES ARE IN PLACE
09/18/2018 ELECTRIC - INTERMEDIATE Partial Approval BUILDING #2, LEVEL #8 WEST SLAB. CONDUITS AND BOXES IN PLACE. OK TO COVER.
09/10/2018 ELECTRIC - INTERMEDIATE Partial Approval BUILDING #2, LEVEL #8 EAST: CONDUITS AND BOXES ARE IN PLACE. OK TO PLACE CONCRETE.
09/06/2018 ELECTRIC - INTERMEDIATE Partial Approval BUILDING #2, SLAB AT LEVEL #7, GL: G-N/2-12; CONDUITS AND BOXES IN PLACE. OK TO PLACE CONCRETE.
09/06/2018 ELECTRIC - INTERMEDIATE Partial Approval IN WALLS OF BUILDING #3, LEVEL #2. OK TO COVER WALLS. BUILDING #2, LEVEL #7 WEST, CONDUITS AND BOXES IN PLACE. OK TO PLACE CONCRETE.
08/27/2018 ELECTRIC - INTERMEDIATE Partial Approval GARAGE SLAB AT LEVEL #6 AT GL: 3-12/N-Y. OK TO COVER CONDUITS AND BOXES.
08/23/2018 ELECTRIC - INTERMEDIATE Cancelled CANCELLED: CONTRACTOR CANCELLED
08/23/2018 ELECTRIC - INTERMEDIATE Partial Approval IVRS - Inspection :* BUILDING #2, LEVEL #6, CONDUITS AND BOXES IN SLAB. OK TO COVER PARTIAL
08/16/2018 ELECTRIC - INTERMEDIATE Partial Approval BUILDING #2, LEVEL #6 EAST: CONDUITS AND BOXES IN SLAB. OK TO COVER.