Permit: T17CM04612

Parcel: 124071390


Addresses:

55 N PARK AV BLDG#1

Inspection Status: Approved

Inspection History: BUILDING - PROGRESS

Date Description Inspector Results Comments
07/23/2019 BUILDING - PROGRESS Approved
07/22/2019 BUILDING - PROGRESS Partial Approval Roof inspections for buildings #1-3 for pre Certificate of Occupancy inspection.
07/20/2019 BUILDING - PROGRESS Partial Approval Pre Certificate of Occupancy inspection of rooms, corridors, and Amenities area: Building #2; Levels #6, 7, 8.
07/19/2019 BUILDING - PROGRESS Partial Approval Building #2; Level #5: Rooms and corridors pre-Certificate of Occupancy inspections. Temporary Certificate of Occupancy for Leasing office inspection. Ok for staff to occupy office areas.
07/17/2019 BUILDING - PROGRESS Partial Approval Room check for proposed building final at building #2; Level #1: rooms and corridors.
07/16/2019 BUILDING - PROGRESS Partial Approval Pre-building final. Student rooms and corridors in building #1; Levels #1-4. Living areas are complete. Parking garage Levels #1-4; two exit signs on level #3 need to be moved(sign view obstructed by fire sprinkler pipe); mark (paint) change in slab height in end unit parking places.
07/15/2019 BUILDING - PROGRESS Cancelled Called Jim Burge to confirm he will do these inspections.
07/12/2019 BUILDING - PROGRESS Partial Approval Building #3, Levels #1-4 room and common areas check for pre-building final. Items that need corrections have been noted and are to be addressed.
07/03/2019 BUILDING - PROGRESS Partial Approval Information only...exterior hand rails.
06/28/2019 BUILDING - PROGRESS Partial Approval Building #3; walk through of common areas for pre-building Final.
06/25/2019 BUILDING - PROGRESS Partial Approval Information only, scheduling for furniture move in.
06/18/2019 BUILDING - PROGRESS Partial Approval Building #2; Level #8: student rooms. Electric inspections for Temporary Certificate of Occupancy for moving in furniture and related equipment. Not for Occupancy. Rooms: 2802; 2803; 2804; 2806; 2807; 2808; 2809; 2810; 2811; 2812; 2813; 2814; 2815; 2816; Ok to make application for Temporary Certificate of Occupancy.
06/17/2019 BUILDING - PROGRESS Partial Approval Electric inspections for rooms in Building #2, Level 7 for Temporary Certificate of Occupancy for moving in furniture and related equipment. Not for occupation. Rooms: 2702; 2703; 2704; 2705: 2706; 2707; 2708; 2713; 2716; 2718.
06/14/2019 BUILDING - PROGRESS Partial Approval Building #2; Level #6: Rooms 2602; 2603; 2604; 2605; 2606; 2607; 2611; 2612; 2613; 2615; 2616; 2618. Electric inspections for application for Temporary Certificate of Occupancy, moving in furniture and related equipment. Not for Occupancy.
06/13/2019 BUILDING - PROGRESS Partial Approval Electric inspections of rooms for Temp C of O for moving in furniture and related equipment. Building #2; Level #5; Rooms; 2501; 2502; 2503; 2504; 2505; 2506; 2507; 2513; 2515; 2516; 2518.
06/12/2019 BUILDING - PROGRESS Partial Approval Electric Room check for application for Temporary Certificate of Occupancy for moving in furniture and related equipment: Building #2; Level #4; Rooms: 2401; 2402; 2403; 2405; 2406; 2407; 2413; 2414; 2415; 2416; 2417; 2418.
06/11/2019 BUILDING - PROGRESS Partial Approval Electric inspection for application of Temporary certificate of occupancy for moving in furniture and related equipment only...Not for occupancy. Building #2; Level #3; Rooms #2301; 2302; 2303; 2304: 2326; 2317; 2318.
06/07/2019 BUILDING - PROGRESS Partial Approval Electric Room check for application of Temporary Certificate of Occupancy for moving in furniture and related equipment. Not for Occupancy.
Building #2; Level #2; Rooms: 2207; 2213. Level #3; Rooms: 2305; 2305; 2307; 2313; 2314; 2315.
06/06/2019 BUILDING - PROGRESS Partial Approval Electrical inspection of rooms for application for Temporary Certificate of Occupancy to move in furniture and related equipment: Building #2; Level #2; Rooms: 2204, 2205; 2206; 2214; 2215; 2216.
06/04/2019 BUILDING - PROGRESS Partial Approval Electric Room check for application for Temporary Certificate of Occupancy to move in furniture and related equipment. Building #2, Level #1, Rooms: 2107, 2113, 2114; Level #2, Rooms: 2201, 2202, 2203, 2217, 2218.
05/31/2019 BUILDING - PROGRESS Partial Approval Building #2, Level #1, Rooms #2101-2105; 2115-2118. Electric inspection of outlets for application of Temporary Certificate of Occupancy for moving in furniture and related equipment.
05/29/2019 BUILDING - PROGRESS Partial Approval Building #2; Level #1. Rooms #2101, 2102, 2104, 2104, 2105, 2115, 2116, 2118. Room electrical outlets were tested for moving in furniture and related equipment for a Temporary Certificate of Occupancy.
05/28/2019 BUILDING - PROGRESS Not ready for Inspection Contractor cancelled. Building #2 is not ready for TCO Inspection.
05/23/2019 BUILDING - PROGRESS Partial Approval Building #1, Levels #3-4. Room check for partial electric for moving in furniture and related equipment. Ok to make application for Temporary Certificate of Occupancy for furniture move in only; not for occupancy.
05/22/2019 BUILDING - PROGRESS Partial Approval Walked building number one rooms 1101 through 1108 and 1201 through 1208 OK to apply for temp c of o pending fire in engineering for stocking furniture only.
05/21/2019 BUILDING - PROGRESS Partial Approval Building #3; Levels #1-4; Pre-Temporary Certificate of Occupancy room inspections for moving in furniture and related equipment. Not for Occupancy. Ok to make application for TCO when fire inspections are complete.
05/20/2019 BUILDING - PROGRESS Partial Approval Building #3, Levels 2-4; inspections for Temporary Certificate of occupancy for moving in furniture and related equipment only. Not for occupation.
05/17/2019 BUILDING - PROGRESS Partial Approval Room inspections for TCO to move furniture and equipment into Building #1. Building #1; Level #4; Rooms. 1401-1408.
05/13/2019 BUILDING - PROGRESS Partial Approval Pre- temporary certificate of occupancy walk through for Buildings #1 & #3.
04/15/2019 BUILDING - PROGRESS Partial Approval All openable windows will be required to have a 4" safety block installed
03/21/2019 BUILDING - PROGRESS Not ready for Inspection Contractor cancelled. No inspections for today
03/18/2019 BUILDING - PROGRESS Not ready for Inspection No inspections for today. Contractor cancelled
12/04/2018 BUILDING - PROGRESS Partial Approval Garage: Level 7 (west deck) metal deck system - puddle welded throughout. Ok to place concrete.
12/03/2018 BUILDING - PROGRESS Not ready for Inspection Contractor cancelled.