Inspection History Details
Inspection Status: Approved
Inspection History: SHEET ROCK NAILING
Permit Number - T17CM04612
Inspection Description - SHEET ROCK NAILING
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/18/2019 | SHEET ROCK NAILING | Approved | ||
| 04/17/2019 | SHEET ROCK NAILING | Partial Approval | Amenities Building, study rooms: walls and ceilings. Ok to tape Throughout. |
|
| 04/11/2019 | SHEET ROCK NAILING | Partial Approval | Building #2, Level #8 corridors and walls. Study hall walls and ceilings. Ok to tape progress areas. | |
| 04/02/2019 | SHEET ROCK NAILING | Partial Approval | Ceiling level six gymnasium OK to tape | |
| 03/27/2019 | SHEET ROCK NAILING | Partial Approval | All drywall in leasing office OK to tape | |
| 03/20/2019 | SHEET ROCK NAILING | Not ready for Inspection | Contractor cancelled, no inspections for today | |
| 03/19/2019 | SHEET ROCK NAILING | Partial Approval | Building #2, Level #7, walls and ceilings in corridors. Building #2, Level #8, walls only. Ok to tape progress areas | |
| 03/15/2019 | SHEET ROCK NAILING | Partial Approval | Amenities Building, Level #6. Ok to Sheetrock walls | |
| 03/13/2019 | SHEET ROCK NAILING | Partial Approval | Building #2, Level #6; Ramp corridor to amenities area. Building #1, Level #3, Bicycle storage rooms, men’s and women’s restrooms. Amenities building, study rooms ceilings. Ok to tape progress areas. | |
| 03/12/2019 | SHEET ROCK NAILING | Partial Approval | Building #2, Level #8, Rooms #2812, 2813, 2814, 2816. Ok to tape progress areas. | |
| 03/11/2019 | SHEET ROCK NAILING | Partial Approval | Building #2, Level #8, Rooms 2807, 2808, 2809, 2810, 2811, ok to tape progress areas. | |
| 03/08/2019 | SHEET ROCK NAILING | Not ready for Inspection | contractor cancelled | |
| 03/06/2019 | SHEET ROCK NAILING | Not ready for Inspection | Contractor cancelled. Will reschedule for 7 March. | |
| 03/05/2019 | SHEET ROCK NAILING | Not ready for Inspection | Contractor cancelled. | |
| 03/04/2019 | SHEET ROCK NAILING | Not ready for Inspection | ||
| 03/01/2019 | SHEET ROCK NAILING | Partial Approval | Partial. Building #2, Level #8, Rooms 2802, 2803, 2804, 2806; 2602 Ok to tape progress areas. |
|
| 02/28/2019 | SHEET ROCK NAILING | Not ready for Inspection | Contractor cancelled. | |
| 02/26/2019 | SHEET ROCK NAILING | Partial Approval | Building #2, Level #6, corridor ceilings; Level #7, corridor walls. OK to tape progress areas. |
|
| 02/25/2019 | SHEET ROCK NAILING | Not ready for Inspection | Contractor cancelled. | |
| 02/21/2019 | SHEET ROCK NAILING | Partial Approval | Building #2, Level #7, Rooms 2703, 2704, 2705, Ok to tape progress areas. | |
| 02/20/2019 | SHEET ROCK NAILING | Partial Approval | Building #1, Level #4, Rooms 1404, 1406, 1407, 1408. Ok to tape progress areas. | |
| 02/19/2019 | SHEET ROCK NAILING | Partial Approval | Units 2708, 2707, 2706, 2705, 2700 (bicycle storage) 2502, and six floor Corredor OK to tape. | |
| 02/14/2019 | SHEET ROCK NAILING | Partial Approval | Building #2, Level #7, Rooms: 2711-2718. Building #1, Level #4, Rooms: 1401, 1402, 1403, 1405 and corridor. Ok to tape progress areas | |
| 02/11/2019 | SHEET ROCK NAILING | Partial Approval | Building #2, Level #5, corridors - Ok to tape progress areas. | |
| 02/08/2019 | SHEET ROCK NAILING | Partial Approval | Building #2, Level #6, Rooms 2611-2612. Ok to tape progress areas. | |
| 02/05/2019 | SHEET ROCK NAILING | Partial Approval | Building #1, Level #3, Rooms and corridor. Ok to tape progress areas. | |
| 01/31/2019 | SHEET ROCK NAILING | Partial Approval | Building #2, Level #6, Rooms 2603 - 2607 and corridors. Ok to tape progress areas. | |
| 01/29/2019 | SHEET ROCK NAILING | Partial Approval | Building #1, Level #2. Rooms and corridor. Ok to tape progress areas. | |
| 01/25/2019 | SHEET ROCK NAILING | Not ready for Inspection | Contractor cancelled. | |
| 01/23/2019 | SHEET ROCK NAILING | Partial Approval | Level #5, corridors; Level #6: Rooms 2615, 2616, 2518, 2613. Ok to tape progress areas. | |
| 01/22/2019 | SHEET ROCK NAILING | Partial Approval | Building #1, Level #2 Rooms: 1201-1204; 1206-1208; Level #1, Corridors. Ok to tape progress areas. | |
| 01/16/2019 | SHEET ROCK NAILING | Partial Approval | Building #1, Level #4; Rooms 1103; 1104; 1105; 1106. Building #2; Level #5, rooms 2501-2504. | |
| 01/11/2019 | SHEET ROCK NAILING | Partial Approval | Building 2, Level 5. Rooms #2506, 2507, 2513, 2525. Building #1. Level 1, Rooms 1101, 1102, 1107, 2108. Ok to tape progress areas. | |
| 01/08/2019 | SHEET ROCK NAILING | Partial Approval | Building #2; Level #5: Rooms 2516, 2517, 2518. Ok to tape progress areas. | |
| 01/07/2019 | SHEET ROCK NAILING | Not ready for Inspection | Contractor cancelled. | |
| 01/04/2019 | SHEET ROCK NAILING | Partial Approval | Corders level four OK to finish drywall | |
| 12/27/2018 | SHEET ROCK NAILING | Partial Approval | Building #2, Level #4. Rooms: 2401 - 2407. Ok to tape progress areas. | |
| 12/20/2018 | SHEET ROCK NAILING | Not ready for Inspection | Contractor cancelled. | |
| 12/19/2018 | SHEET ROCK NAILING | Partial Approval | Building #2, Level #4: Rooms. 2413 - 2418. Ok to tape progress areas. | |
| 12/17/2018 | SHEET ROCK NAILING | Partial Approval | Building #2, Level #3 corridors. Ok to tape progress areas. | |
| 12/10/2018 | SHEET ROCK NAILING | Partial Approval | Building #2. ,Leve 3, rooms #2301-2307 | |
| 12/03/2018 | SHEET ROCK NAILING | Partial Approval | Building #2, Level #3 South: Rooms #2314-2318. Ok to tape progress areas. | |
| 11/29/2018 | SHEET ROCK NAILING | Partial Approval | Building #2, Level #2. Corridors. Ok to tape progress areas. | |
| 11/20/2018 | SHEET ROCK NAILING | Partial Approval | Building #2; Level #2; Rooms #2201, 2203-2207. Ok to tape progress areas. | |
| 11/15/2018 | SHEET ROCK NAILING | Partial Approval | Building #2; Level #5. Exterior sheetrock. Ok to cover progress areas. | |
| 11/13/2018 | SHEET ROCK NAILING | Partial Approval | Building #2, Level 2, Rooms #2213 - 2218. Ok to tape progress areas. | |
| 11/08/2018 | SHEET ROCK NAILING | Partial Approval | Building #2, Level #1. Corridors. Ok to tape progress areas | |
| 11/05/2018 | SHEET ROCK NAILING | Partial Approval | Building #2, Level #1, Rooms 2101-2105. Ok to tape progress areas. | |
| 11/02/2018 | SHEET ROCK NAILING | Not ready for Inspection | Contractor cancelled. | |
| 11/01/2018 | SHEET ROCK NAILING | Not ready for Inspection | Contractor cancelled. | |
| 10/26/2018 | SHEET ROCK NAILING | Not ready for Inspection | Contractor cancelled | |
| 10/25/2018 | SHEET ROCK NAILING | Partial Approval | Units 2113 through 2115 OK to cover | |
| 10/22/2018 | SHEET ROCK NAILING | Partial Approval | Building #3, Level #4; rooms and corridor. Ok to tape progress areas | |
| 10/09/2018 | SHEET ROCK NAILING | Partial Approval | Building #3, Level 2; rooms and corridor. Ok to tape progress areas | |
| 10/05/2018 | SHEET ROCK NAILING | Partial Approval | Building #2, Level #4; exterior sheathing. Pk to waterproof. | |
| 09/27/2018 | SHEET ROCK NAILING | Partial Approval | Building #3, Level, # 1, Rooms and corridor. OK to tape progress areas. | |
| 09/25/2018 | SHEET ROCK NAILING | Partial Approval | BUILDING #2, EMERGENCY ELECTRIC ROOM. OK TO TAPE. | |
| 09/20/2018 | SHEET ROCK NAILING | Not ready for Inspection | WORK INCOMPLETE |