Permit: T17CM04612

Parcel: 124071390


Addresses:

55 N PARK AV BLDG#1

Inspection Status: Approved

Inspection History: FRAMING

Date Description Inspector Results Comments
07/23/2019 FRAMING Approved
03/27/2019 FRAMING Partial Approval Maintenance restroom in basement OK to cover interior walls. Plumbing re-vent on north wall needs continuous grade for gravity venting.
02/04/2019 FRAMING Partial Approval Building #3, leasing area, Building #4 interior framing.
01/30/2019 FRAMING Partial Approval Building #3, Leasing area; Building #4, interior framing
11/02/2018 FRAMING Partial Approval Building #1, Level 2 deck. Ok to place wall framing
(reopenED 1035 to read partial-PER JBURGE)
10/31/2018 FRAMING Partial Approval Building #1, Level #1: Rooms and corridor.
10/23/2018 FRAMING Partial Approval Building #1, Level #2 deck; nailing and straps. Ok to proceed with interior framing
10/05/2018 FRAMING Partial Approval Building #2, Level #4; Exterior framing. Ok to cover.
09/20/2018 FRAMING Not ready for Inspection WORK INCOMPLETE. RESCHEDULED FOR. 9.21.
09/19/2018 FRAMING Partial Approval BUILDING #2, EXTERIOR, LEVEL #4: OK TO COVER PROGRESS AREAS,
09/18/2018 FRAMING Cancelled
09/13/2018 FRAMING Partial Approval BUILDING #3, LEASING OFFICE AREA - METAL FRAMING.
08/30/2018 FRAMING Partial Approval BLDG 2 LEVEL 3 OK TO COVER EXTERIOR WALLS
08/17/2018 FRAMING Partial Approval BUILDING #2; EXTERIOR WALLS AT LEVEL #2 - OK TO COVER PROGRESS AREAS. BUILDING #3, LEVEL #4 INTERIOR FRAMING.
08/16/2018 FRAMING Partial Approval BUILDING #2, LEVEL #1: EXTERIOR METAL FRAMING. OK TO COVER PROGRESS AREAS.
08/14/2018 FRAMING Partial Approval BUILDING #3, LEVEL #2.
07/31/2018 FRAMING Partial Approval BUILDING #3, LEVEL #4, SUB-DECKING - OK TO FRAME WALLS.
07/30/2018 FRAMING Partial Approval BUILDING #3, LEVEL #2, FRAMING IS COMPLETE.
07/27/2018 FRAMING Cancelled CONTRACTOR CANCELLED.
07/25/2018 FRAMING Cancelled CONTRACTOR CANCELLED. WORK INCOMPLETE.
07/13/2018 FRAMING Partial Approval BUILDING #3, LEVEL #1, CLIPS AND STRAPS ARE IN PLACE.
07/12/2018 FRAMING Cancelled CONTRACTOR CANCELLED.
07/06/2018 FRAMING Not ready for Inspection WILL RESCHEDULE FOR 9 JULY 2018
06/13/2018 FRAMING Partial Approval BUILDING #1, LEVEL #4 DECK; NAILED AND STRAPPED. OK TO COVER.
06/08/2018 FRAMING Partial Approval BUILDING #1, LEVEL #2, INTERIOR STRAPS AND CLIPS.
05/31/2018 FRAMING Partial Approval BUILDING #1, LEVEL 3 DECKING - (NORTH AND SOUTH)
05/25/2018 FRAMING Partial Approval BUILDING #1, LEVEWL #1: INTERIOR STRAPS AND CLIPS; SHEAR WALLS NAILING AND CLIPS.
05/21/2018 FRAMING Partial Approval BUILDING #1, LEVEL #2 DECK, SOUTH PORTION - OK TO SET WALL FRAMING.
05/15/2018 FRAMING Partial Approval BUILDING #1, EXTERIOR SHEATHING (FIRST LAYER)*; LEVEL #2 DECK - NORTH HALF. *EXTERIOR SHEATHING: POSSIBLE ADDITION OF 1/4" VANEER SHEATHING TO MAKE EXTERIOR WALLS 7/16" AS PER PLAN. AWAITING APPROVAL FROM ARCHITECT.