| 07/23/2019 |
BUILDING PRE-SLAB |
|
Approved |
|
| 10/24/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
Building #2, Level #9 slab. Ok to place concrete |
| 10/10/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
Building #2, Level #8, GL: N - Y/2 - 12; Post tension cable system. Cables: Banded - 122 ; Uniform - 132 |
| 10/01/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
Building #2, Level #9 West: GL: B-G/2-12. Ok to place concrete. |
| 09/26/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
Garage Level #7 at GL: 2 - 10/N -Y. Ok to place concrete. |
| 09/24/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
BUILDING #2, LEVEL #9 eAST SLAB. OK TO PLACE CONCRETE. |
| 09/10/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
BUILDING #2, 8 EAST: POST TENSION CABLE SYSTEM - GL: G-N/2-12. OK TO PLACE CONCRETE. |
| 09/06/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
BUILDING #2, LEVEL #7 EAST AT GL: G-N/2-12; SHEAR WALL #10. OK TO PLACE CONCRETE. |
| 08/27/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
GARAGE: LEVEL #6, DOUBLE MAT REBAR AT GL: 3-12/N-Y. OK TO PLACE CONCRETE. |
| 08/23/2018 |
BUILDING PRE-SLAB |
|
Cancelled |
CANCELLED: CONTRACTOR CANCELLED |
| 08/23/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
IVRS - Inspection :* BUILDING #2 LEVEL #6, GL: A-G/1-12. TENDON COUNT: UNIFORM: 125, BANDED: 155. OK TO PLACE CONCRETE. |
| 08/16/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
BUILDING #2, LEVEL #6 EAST; GL: G - N/2 - 12. OK TO PLACE CONCRETE. SHEAR WALL #10 - OK TO PLACE CONCRETE. |
| 08/02/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
LEVEL #5, WEST: POST TENSION CABLE SYSTEM AT GL: G - N/1 - 12. OK TO PLACE CONCRETE. |
| 07/31/2018 |
BUILDING PRE-SLAB |
|
Cancelled |
|
| 07/27/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
POST TENSION CABLE SYSTEM,. BUILDING #2, LEVEL #4, GL: 1-12/A-G. OK TO PLACE CONCRFETE. CABLES: BANDED 169 UNIFORM 135. |
| 07/16/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
BUILDING #3, WOOD DECK AT LEVEL #3. BUILDING #3, LEVEL #3 DOUBLE MAT REBAR AT GL: 1.5 - 6/Y - Z. OK TO PLACE CONCRETE. |
| 06/18/2018 |
BUILDING PRE-SLAB |
|
Cancelled |
CONTRACTOR CANCELLED DUE TO HEAVY RAINS 6-16-18 |
| 06/14/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
GARAGE: LEVEL #5 AT GL: O - S/12.5 - 15.5 (MID DECK). OK TO PLACE CONCRETE. |
| 06/11/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
BUILDING #2, LEVEL #4 EAST: POST TENSION CABLE SYSTEM AT GL: G-N/1-12.1. OK TO PLACE CONCRETE. AFTER HOURS INSPECTION (3:00 PM - 5:00 PM). CHARGE UEB APA ACCOUNT $165.00 FOR INSPECTION. |
| 06/04/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
BUILDING #2, LEVEL #3-EAST: POST TENSION CABLE SYSTEM - CABLES: BONDED: 176; TYPICAL: 131. OK TO PLACE CONCRETE. |
| 05/30/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
GARAGE, LEVEL #6, LOWER POOL DECK (POUR #1) AT GL: S-Y/11-15.3. OK TO PLACE CONCRETE. |
| 05/25/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
BUILDING #3 EAST, POST TENSION CABLE SYSTEM - GL: G-N/1-12: CABLES: 122 BONDED; 85 TYPICAL. ELECTRIC CONDUITS AND BOXES IN SLAB. OK TO PLACE CONCRETE. |
| 05/24/2018 |
BUILDING PRE-SLAB |
|
Cancelled |
CONTRACTOR CANCELLED. |
| 05/18/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
BUILDING #2, LEVEL #2: POST TENSION CABLE SYSTEM; AT GL: A-G/1-12. OK TO PLACE CONCRETE. |
| 05/16/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
GARAGE LEVEL #4, PART "C"; GL: 12-17/N-Y. OK TO PLACE CONCRETE. CABLES: BANDED: 105; UNIFORM: 98 |
| 05/12/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
LEVEL 3 GRIDLINE G TO N - 0 TO 12 OK TO PLACE CONCRETE. |
| 05/11/2018 |
BUILDING PRE-SLAB |
|
Cancelled |
|
| 05/09/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
POST TENSION CABLE SYSTEM AT LEVEL #4, SECTION "B". OK TO PLACE CONCRETE. |
| 05/02/2018 |
BUILDING PRE-SLAB |
|
Cancelled |
|
| 04/25/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
LEVEL #3, SECTION "B"; GL: N - Y/1.5 - 11. POST TENSION CABLE SYSTEM IN SLAB. OK TO PLACE CONCRETE. |
| 04/19/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
BUILDING #2, SLAB ON GRADE AT GL: A - F/1 - 12.1: OK TO PLACE CONCRETE. |
| 04/18/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
POST TENSION CABLE SYSTEM ON LEVEL #2, SECTION "C" AT GL: N-Y/12-17. OK TO PLACE CONCRETE. |