Permit: T17CM04612

Parcel: 124071390


Addresses:

55 N PARK AV BLDG#1

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
07/23/2019 EXCAVATION/LAYOUT REBAR & ZON Approved
05/01/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval
04/26/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval SW corner of bldg 2, retaining wall.
03/28/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval OK to pour footings for retaining wall on East side of building three
03/08/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Footings for sidewalk and ramp area at GL: Z/3-5. Ok to place concrete.
03/07/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Contractor cancelled
03/06/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Contractor cancelled.
11/20/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Contractor cancelled
11/16/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Contractor cancelled.
11/14/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Garage: Level #1, Elevator Landing at GL: W.9/6. Ok to place concrete.
11/08/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Contractor cancelled.
11/05/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Amenities building footings and column footings. Ok to place concrete in progress areas.
11/02/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Garage: Level #2, GL: M-N/9-13; Hanging wall at Level #3, GL:1.5/0'-6'. OK to place concrete.
10/24/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Building #2, Level #9; Post tension cable system. Ok to cover
10/19/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Building #2, Stair #2-1, treads at Level #1 to Level #9. Wire mesh in place, ok to place concrete
10/18/2018 EXCAVATION/LAYOUT REBAR & ZON Cancelled
10/12/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Building #1, 8 each pedestals at GL: 14/A - L. OK to place concrete
10/10/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Building #2, Level #8, GL: N - Y/2 - 12; Post tension cable system. Cables: Banded - 122 ; Uniform - 132.
10/08/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Garage stem wall at GL: M/10 - 12, 2 EACH CW-5 columns at GL: M/11 - 13. OK to place concrete.
10/04/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Building #2, 8 column footings at GL: 14/A-L. OK to place concrete.
09/28/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Garage, Level #7; 23 columns at GL: N-Y/2-12; shear walls #11, 11A, 11B. Ok to place concrete.
09/27/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection CONTRACTOR CANCELLED
09/25/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection CONTRACTOR CANCELLED
09/24/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection CONTRACTOR CANCELLED
09/18/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval LEVEL 8 COLUMNS - 18 ON WEST SIDE OK TO POUR. ALSO SHEARWALLS 1,2,3 OK TO POUR.
09/17/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #2, LEVEL 8 WEST - POST TENSION CABLE SYSTEM. OK TO PLACE CONCRETE.
09/14/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GARAGE ENTRY RAMP AT GL: W-U/16-17. REQUIRED TO REINFORCE AREA WITH WIRE MESH. OK TO PLACE CONCRETE.
09/13/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GARAGE- STAIR WELL #3-1 (WIRE MESH) AT LANDINGS AND STAIRS: OK TO PLACE CONCRETE.
09/12/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #2, LEVEL #8 EAST; 8 COLUMNS AT GL: 3-12/G-L; SHEAR WALLS #4 AND #10 AT LEVELS #8 TO ROOF. OK TO PLACE CONCRETE.
09/11/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GARAGE AT LEVEL #6, POOL AREA. GL: 14-16/T-V. OK TO PLACE CONCRETE.
09/11/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #2, LEVEL #8 EAST: 13 COLUMNS AT GL: 3-11/H-N. OK TO PLACE CONCRETE.
09/10/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GARAGE: LEVEL #6, GL: N-W/2-4.5; DOUBLE MAT SYATEM. OK TO PLACE CONCRETE.
09/06/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #2 LEVEL #7 WEST; POST TENSION CABLE SYSTEM. OK TO PLACE CONCRETE.
09/06/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GARAGE, LEVEL#6: GL: 2-9/N-Y, 8 COLUMNS. BUILDING #2, LEVEL #7 WEST: 26 COLUMNS AT GL: 2-12/B-G; SHEAR WALLS #1, 2, 3; LEVELS 7 TO 8. OK TO PLACE CONCRETE.
09/04/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GARAGE: LEVEL #6, SLAB #4-3 NORTH. OK TO PLACE CONCRETE.
08/30/2018 EXCAVATION/LAYOUT REBAR & ZON Cancelled
08/29/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #2, LEVEL #7 EAST: 24 COLUMNS, 1 SHEAR WALL#4, AT GL: G.5-N/2/12.1. OK TO PLACE CONCRETE.
08/27/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GARAGE: LEVEL #6, DOUBLE MAT REBAR AT GL: 3-12/N-Y. OK TO PLACE CONCRETE.
08/24/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #2, 26 COLUMNS AND 3 SHEARWALLS: GL: B-G/2-12; SHEAR WALLS #1, 2, 3. OK TO PLACE CONCRETE.
08/21/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval PARKING GARAGE LEVEL 6 COLUMNS CC13 GL 12 / R TO T (2 COLS) OK TO POUR.
08/20/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #2, LEVEL #6 COLUMNS AT GL: N/7; CRASH WALLS AT GARAGE LEVELS #2 AND #3 AT GL: Y/5-15.5. GARAGE LEVEL #1, SLAB AT GL: W.5-Y/1-3; 8" SLAB AT GARAGE LEVEL #1, STAIRWELL G-2. OK TO PLACE CONCRETE.
08/17/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #2, LEVEL #6 EAST - 25 COLUMNS AT GL: H-N/2-12; SHEAR WALL #4 - OK TO PLACE CONCRETE.
08/15/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection WORK INCOMPLETE.
08/14/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GARAGE: LEVELS: #1 - 3, LANDINGS - REINFORCEMENT; OK TO PLACE CONCRETE.
08/13/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #2, LEVEL #5; 25 COLUMNS AT GL: A-G/1-12; SHEAR WALL #1, LEVEL #5-6 AT GL; B/4-6. POUR BACK AT GARAGE LEVEL #3, NORTH AT GL:N/15.5. OK TO PLACE CONCRETE.
08/11/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #2, LEVEL #5; 10 COLUMNS AT GL: 11/D.3; 10/C.3-G; D.7;; E/6, F/4.2; 4/E: SHEAR WALLS #2 AND #3. OK TO PLACE CONCRETE
08/09/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GARAGE: LEVEL #6, POUR #3; GL: 12-13/N-T; 6-12/T-Y; GARAGE LEVEL #, SHEARWALL #10. OK TO PLACE CONCRETE.
08/06/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #2, LEVEL #5 SOUTH: 16 COLUMNS AT GL: 2-12/G-N; OK TO PLACE CONCRETE.
08/04/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 8 COLUMNS AT GL: J/6, L/11, L/10, L/8.3, L/7, M/4, N/7-4.2: SHEAR WALL #4 AT GL: 8.5- 10/J. OK TO PLACE CONCRETE.
AFTER HOURS INSPECTION ON THIS DATE; CHARGED APA ACCOUNT $165.
08/03/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval LEVEL #3, CRASH WALL AT GL: N/3 - 6; OK TO PLACE CONCRETE.
07/31/2018 EXCAVATION/LAYOUT REBAR & ZON Cancelled
07/30/2018 EXCAVATION/LAYOUT REBAR & ZON Cancelled CONTRACTOR CANCELLED. INSPECTION PERFORMED ON 28 JULY 2018.
07/28/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #2, LEVEL #4, 18 COLUMNS AT GL: 9/A-C.4; A/9-3; 4/C-3, SHEAR WALL #2. OK TO PLACE CONCRETE. AFTER HOURS INSPECTION ON 28 JULY.
07/27/2018 EXCAVATION/LAYOUT REBAR & ZON Cancelled CONTRACTOR CANCELLED
07/27/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #2, LEVEL #4, 16 COLUMNS AT GL: 3 - 12/C - G; SHEAR WALL #3 AT 6/F-G. OK TO PLACE CONCRETE.
07/25/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GARAGE , LEVEL #5. COLUMNS: CC13 AT T/12; CC18 AT T.8/12. OK TO PLACE CONCRETE.
07/24/2018 EXCAVATION/LAYOUT REBAR & ZON Cancelled CONTRACTOR CANCELLED - WORK INCOMPLETE
07/19/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GARAGE, LEVL #2; CRASH WALLS AT GL: N/2-15. OK TO PLACE CONCRETE.
07/18/2018 EXCAVATION/LAYOUT REBAR & ZON Cancelled CONTRACTOR CANCELLED. WORK INCOMPLETE.
07/17/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GARAGE: LEVEL #4 - LEVEL #5: SHEAR WALL #11, 11A, 11B. POUR BACK AT LEVEL #4, GL: 9/N-T. OK TO PLACE CONCRETE.
07/13/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GARAGE LEVELS #3.5 & 4: POUR BACKS. OK TO PLACE CONCRETE.
07/12/2018 EXCAVATION/LAYOUT REBAR & ZON Cancelled CONTRACTOR CANCELLED
07/11/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval LEVELS # 1-3, COLUMN #CC22 AT GL:Z/1.5. OK TO PLACE CONCRETE.
07/10/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN AT LEVEL #1, BUILDING #3: GL: Y/4.2 (CW5) AT LEVELS #1 - 3. OK TO PLACE CONCRETE.
07/09/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CRASH WALL AT Y/7 - 15.5 ON LEVEL #1, OK TO PLACE CONCRETE.
07/06/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval RAMP WALL AT GL: Y/8-15.5 (EAST): COLUMNS AT BUILDING #3 AT GL: Y-Z/3-4. OK TO PLACE CONCRETE.
06/20/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection NOT READY DUE TO FIRE ON SITE.
06/19/2018 EXCAVATION/LAYOUT REBAR & ZON Cancelled CONTRACTOR CANCELLED DUE TO FIRE AT BUILDING #2.
06/18/2018 EXCAVATION/LAYOUT REBAR & ZON Cancelled CONTRACTOR CANCELLED DUE TO HEAVY RAINS 6-16-18
06/15/2018 EXCAVATION/LAYOUT REBAR & ZON Cancelled
06/14/2018 EXCAVATION/LAYOUT REBAR & ZON Cancelled CONTRACTOR CANCELLED.
06/13/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #2, LEVEL #4: COLUMNS: 13 COLUMNS AT GL: G-N/1-9. OK TO PLACE CONCRETE.
06/12/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #2, LEVEL #4 EAST: COLUMNS (15) AT GL: H-N/3-12.1. SHEAR WALL #4, LEVELS 4-5: GL: J/8.5-10. OK TO PLACE CONCRETE.
06/11/2018 EXCAVATION/LAYOUT REBAR & ZON Cancelled
06/08/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #3, STEM WALL AT GL: Y-Z/1.5-6. OK TO PLACE CONCRETE.
06/07/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GARAGE: LEVEL 2 EAST AND WEST (POUR STRIPS): LEVEL #6, SWIMMING POOL AAREA WALLS: GL: T-Y/11-15. SHEARWALL #10, LEVEL 4 TO LEVEL 5 AT GL: N/7-4. OK TO PLACE CONCRETE.
06/06/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #2, LEVEL #3-WEST: COLUMNS: 21 COLUNS AT GL: A-F/1-9. SHEAR WALL #1 AT GL: B.5/3-6 AT LEVELS #3 TO LEVEL #4. SHEAR WALL #2 AT GL: D-E.5/8. WEST POOL WALL AT GL: T/13-15. OK TO PLACE CONCRETE IN PROGRESS AREAS.
06/05/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #2, LEVEL 3-WEST: COLUMNS: 13 @ CC1 , GL: B-G/8-12.5, 1 CC1 @ F/4; SHEAR WALL #3 AT GL: F-G/6 FROM LEVEL #3 TO LEVEL #4. OK TO PLACE CONCRETE.
06/04/2018 EXCAVATION/LAYOUT REBAR & ZON Cancelled CONTRACTOR CANCELLED.
05/30/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #2, LEVEL #3: 29 COLUMNS AT GL: G-N/1-12.5; SHEAR WALL #4 AT GL:9/J. OK TO PLACE CONCRETE.
05/24/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #2, COLUMNS: 4 AT GL: A.5 - C/3-9: SHEAR WALLS IN PARKING GARAGE: LEVEL #4 AT 6' POUR: SW 11, SW11A, SW11B AT GL: Z.9 - Y/2.5 - 4.8. OK TO PLACE CONCRETE.
05/22/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #2, LEVEL #2 TO LEVEL #3, SHEAR WALL #1 AT GL: B.5/3-6; SHEAR WALL #2 AT GL: F-G/6; COLUMNS: 5 @ CC1 AT GL: D-F/11-12. OK TO PLACE CONCRETE.
05/21/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #2, LEVEL #2, SECTION"WEST"; COLUMNS: (13 EACH CC1 AND CC3 COLUMNS) AT GL: C-G/1-10; SHEAR WALL #3, LEVELS 2-3 AT GL: 6/F-G; SHEAR WALL IN GARAGE #7 AT GL: 12/R-T; CRASH WALL AT GARAGE, LEVEL #1, GL: 17/V.5-Y, GARAGE POUR-BACK STRIPS ON LEVELS 1.5 AND LEVEL #2. OK TO PLACE CONCRETE IN PROGRESS AREAS.
05/18/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GARAGE: LEVEL #4, SECTION "B": COLUMNS: 27 2 CC11 AT GL: N-Y/12-17: OK TO PLACE CONCRETE. SHEAR WALL #6 AT LEVEL #4 - 5; GL: 15.5/W-Y. PONY WALL AT GL: 15/T-W AT 24". OK TO PLACE CONCRETE.
05/17/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING#2, LEVEL #2: COLUMNS: 2 @ CC1 AT GL: H/10-12; HEAR WALL #4, GL: LEVEL#2 AND #3, GL: J/8-10; OK TO PLACE CONCRETE.
05/16/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #2, LEVEL #2, COLUMNS: 10 @ CC1 AT 3-12/H.5-N; 2 @ CC4 AT GL: 2/H-L; 1 CC9 AT GL: 2/J; 4 CC5 @ GL: 1/H-L. GARAGE LEVEL #1, CRASH WALL AT GL: 1.5/Q-Y. OK TO PLACE CONCRETE.
05/15/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #2, LEVEL #2, COLUMNS: 2 @ CC1 AT GL: 12/I-K; 2 @ CC1 AT GL: H.4/8-11; 2 @ CC1 AT GL: L/7-9; 2 @ CC1 AT GL: G-I/4. 1 @ AT CC2 AT GL: H.4/3; 1 @ CC10 AT GL: K.5/4. OK TO PLACE CONCRETE.
05/14/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval LEVEL #1, NORTH CRASH WALL AT GL: 17/N - V AT 42" AFFE. COLUMNS: LEVEL #4, SOUTH: 2 @ CC20 AT GL: 2/N - O; 1 @ CC11 AT GL: 2.4/V' 2 @ CC11 AT GL: 4.5/R - U; 2 @ CC12 AT GL: 6/N - O; 1 @CCA9 AT GL: 9/O. OK TO PLACE CONCRETE.
05/11/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval LEVEL 4 COLUMNS 10/N TO Y, 8/R T0 Y, 6/W, 3/N TO O, 2.4/ Q TO T OK TO PLACE CONCRETE
05/10/2018 EXCAVATION/LAYOUT REBAR & ZON Cancelled CONTRACTOR CANCELLED
05/09/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #3, SHEAR WALL #13 AT GL: Y.5 - Z/2.5 AT LEVELS #1 TO LEVEL #2. OK TO PLACE CONCRETE.
05/07/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection CONTRACTOR CANCELLED.
05/04/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval LEVEL #3, SECTION "C" COLUMNS: 8 @ CC11 AT GL: 14/N-Y; 4 @ CC11 AT GL: 13/T-Y; 2 @ CC13 AT GL: 12/W-Y; 2 @ CC11 AT GL: N-O/12; 4 @ CC11 AT GL: N-S/13; 17 @ CC11 AT GL: N-Y/15-17. SHEAR WALLS: SW 5, 6, 7 AT LEVEL #3 - #4. FOOTINGS AT 8 @ F15 FOOTINGS AT GL: 14/A - L. OK TO PLACE CONCRETE.
05/03/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection CONTRACTOR CANCELLED
05/02/2018 EXCAVATION/LAYOUT REBAR & ZON Cancelled
05/02/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMNS CC1 ON GL N/7&9 LEVEL 2 OK TO POUR
04/30/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMNS: LEVEL #3, SECTION "B"; 1 @ CC15 AT GL: W/1.5; 2 @ CC12 AT GL: N/3-6; SHEAR WALL #10 AT LEVELS #3 - 4 AT GL: N/7-9; SHEAR WALL 11, 11A, 11B AT GL: W-Y/2.5-5 AT LEVELS #3 - 4: OK TO PLACE CONCRETE.
04/27/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GARAGE: LEVEL 3, SOUTH COLUMNS (12) AT GL: N-S/2-10.5: OK TO PLACE CONCRETE.
04/26/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GARAGE AT LEVEL #3 SOUTH: 19 COLUMNS AT GL: N-Y/1.5-10.4. OK TO PLACE CONCRETE.
04/25/2018 EXCAVATION/LAYOUT REBAR & ZON Cancelled CONTRACTOR CANCELLED.
04/23/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GARAGE: COLUMNS: LEVEL #2, NORTH, SECTION "C": 3 @ CC11 AT GLl 17/R-W/ 4 @ CC11 AT GL: 16/P-W; 8 @ CC11 AT GL:13 - 14/T - Y; 1 @ CC18 AT T.5/12; 1 @ CC22 AT GL: Z/1.5;
1 @ CC13 AT GL: 12/W; 1 @ CC11 AT GL: 15/U; 2 @ CC11 AT GL: 15.5/N-W. SHEAR WASS #6 AT GL: 15.5/W-Y; SHEAR WALL #5 AT 15/N - O (LEVEL #2 TO LEVEL #3). STEM WALL AT GL: Y-Z/1.5-2.5. OK TO PLACE CONCRETE IN PROGRESS AREAS.
04/20/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval SHEAR WALL #7 AT LEVEL #2 TO LEVEL #3 AT GL: 12/R-T. OK TO PLACE CONCRETE.
04/19/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMNS AT LEVEL #2: GL: 11.8 - 17/Y - N. 16 @ COLUMNS - OK TO SET FORMS AND PLACE CONCRETE.