Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/13/2018 | ELECTRIC - INTERMEDIATE | Approved | ||
| 12/11/2018 | ELECTRIC - INTERMEDIATE | Partial Approval | Framing should not have been approved until the intermediates as mentioned below so change 1035 framing inspection from 11 . 20.2018 to partial approval pending MEP INTERMEDIATE APPROVED AT SAME TIME. Plumbing and mechanical intermediates still need to be inspected which are not ready today plumber is not finished electric is partially approved today and should just be confirmed on the day of the all intermediate inspection which will include framing mechanical electrical and plumbing all at the same time . I explain this to homeowner and they said they will do that. |
|
| 11/30/2018 | ELECTRIC - INTERMEDIATE | Denied | wire is not an inch and a quarter behind framing surface and is not secured. Owner builder to check manufacturers instructions for detail. Foam block. |