Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESS TEST FNL
| Date |
Description |
Inspector |
Results |
Comments |
| 05/28/2019 |
PLUMBING - GAS PRESS TEST FNL |
|
Approved |
OK to clear gas for new service |
| 05/21/2019 |
PLUMBING - GAS PRESS TEST FNL |
|
Partial Approval |
finish installing appliances including water heater and have valves at each appliance. Pressure holding fine. |
| 03/28/2019 |
PLUMBING - GAS PRESS TEST FNL |
|
Partial Approval |
Pressure test OK |