Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/06/2017 | PLUMBING - INTERMEDIATE | Approved | ||
| 07/05/2017 | PLUMBING - INTERMEDIATE | Partial Approval | 1- DWV WATER TEST PROVIDED. 2- P.O.C. OF NEW BLDG. DRAIN TO THE EXISTING BLDG. SEWER IS OKAY. 3- NOTE; THIS INSPECTION IS FOR THE UNDERGROUND ROUGH PLUMBING ONLY. |
|
| 06/30/2017 | PLUMBING - INTERMEDIATE | Partial Approval | 1- UNDERSLAB DWV FITTINGS CAN BE SOLVENT CEMENTED AQND PROVIDE A WATER TEST. | |
| 06/29/2017 | PLUMBING - INTERMEDIATE | Not ready for Inspection | NOT READY FOR INSPECTION | |
| 06/28/2017 | PLUMBING - INTERMEDIATE | Denied | 1- NO ONE HOME AT THE TIME OF INSPECTION REQUEST, NO ACCESS. | |
| 06/27/2017 | PLUMBING - INTERMEDIATE | Denied | IVRS - Inspection : See detailed listing on site.| 999 * |
|
| 06/16/2017 | PLUMBING - INTERMEDIATE | Denied | 1- SHALL PROVIDE DIRECTIONAL FITTINGS FOR UNDERGROUND ROUGH PLUMBING. |