Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Partial Approval
Inspection History: PLUMBING - SEWER HCS CONNECT
| Date |
Description |
Inspector |
Results |
Comments |
| 08/22/2017 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
press testing ok at all lines to existing sewer except final connections to main and man hole tap. |
| 08/22/2017 |
PLUMBING - SEWER HCS CONNECT |
|
Approved |
C.O.- A,B,C,D,E,F,G,H,I,J,K,L,M,N TO MAN HOLE OK |
| 08/21/2017 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
clean out F to main , no connection at this time |
| 08/18/2017 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
clean out D to main sewer , no connection at this time |
| 08/17/2017 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
section clean out A and B and up to main |
| 08/16/2017 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
site sewer as indicated on plans, no test at this time, contractor to air test after back fill |
| 08/14/2017 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
OKAY TO SHADE FROM WEST END TO 20 FT EAST VOF 2ND CLEANOUT. FINAL TEST TO BE AIR. |