Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date |
Description |
Inspector |
Results |
Comments |
| 08/05/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Approved |
|
| 07/23/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
BUILDING #2, PIERS AT E.5-M/1-4, CMU WALL AT 0'- 5' AT GL: N/3-7, N/9-13. OK TO PLACE GROUT. |
| 04/17/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
INSPECTION PERFORMED ON PERMIT T17CM04612 |
| 04/16/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
BUILDING #2, STEM WALLS AT GL: L-N/9-12 AT 0" - 60". OK TO GROUT PROGRESS AREAS. |
| 04/12/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Not ready for Inspection |
CONTRACTOR CNCELLED. |
| 04/11/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
BUILDING #1, STAIRWELL #1-1; CMU WALLS AT 8' - 12: OK TO GROUT. |
| 04/11/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
BUILDING #1, STAIRWELL #1-1: CMU WALLS AT 12'-16'; CMU WALLS AT 0"-48": AT GL: 9/A.5-C. OK TO GROUT PROGRESS AREAS. |
| 04/09/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
CMU WALLS AT 4' - 8' - BUILDING #1, STAIRWELL #1-1. OK TO GROUT PROGRESS AREA. |
| 04/03/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
CMU WALLS AT 0" - 32" AFFE: GL: 15/A-G; 17/A-G; A/14-17; STAIRWELL #11 AT FIRST LIFT AT 0" TO 40" AFFE. OK TO GROUT PROGRESS AREAS. |
| 03/23/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
BUILDING #2, CMU WALLS AT 0" - 48": GL: H-L/12.1, 9-12/H; E.5-H/9; 9-12/F; K-L/1. OK TO PLACE CONCRETE. |
| 03/19/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
FIRST LIFT AT 0"- 48" AT GL: A-F/1-12. OK TO GROUT PROGRESS AREAS. |
| 02/07/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
DOUBLE 12" CMU WALL AT GL: W.9/1.5 - 2.8. AT 0" TO 60". OK TO GROUT PROGRESS AREA. |
| 02/02/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
ELEVATOR #1 AT GL: N.5/15.5, ELEVATOR #2 AT GL: W.5/5 AT LIFT 0" - 48" AFFE. OK TO PLACE GROUT. |