Permit: T17CM03902

Parcel: 124071390


Addresses:

55 N PARK AV


Inspection Status: Approved

Inspection History: BUILDING PRE-SLAB

Permit Number - T17CM03902

Inspection Description - BUILDING PRE-SLAB

Inspection Status - Approved

Date Description Inspector Results Comments
11/20/2018 BUILDING PRE-SLAB Approved Amenities Building, slab and ramps.
06/27/2018 BUILDING PRE-SLAB Partial Approval INFORMATION ONLY: AS PER ALEX ALTMAN RE: BUILDING #3; GTI ENGINEERS HAVE CLEARED BUILDING TO CONTINUE WORK ON 2 JULY 2018.
05/24/2018 BUILDING PRE-SLAB Partial Approval BUILDING #3, AT GL: Y-Z/1.5- 6. OK TO PLACE CONCRETE.
05/14/2018 BUILDING PRE-SLAB Partial Approval BUILDING #3, GL: 6 - 17/V - Z.9. OK TO PLACE CONCRETE.
04/26/2018 BUILDING PRE-SLAB Partial Approval BUILDING #2, SLAB AT G: F-N/1-12.1. OK TO PLACE CONCRETE
04/23/2018 BUILDING PRE-SLAB Partial Approval BUILDING #1, SLAB AT GL: G-N/14-17. OK TO PLACE CONCRETE.
04/11/2018 BUILDING PRE-SLAB Partial Approval GARAGE SLAB AT LEVEL #2, POST TENSION CABLE SYSTEM: SECTION "B" AT GL: N-Y/1-12. OK TO PLACE CONCRETE. CABLES: 207, HAIRPINS: 404.

NOTE: AFTER HOURS INSPECTION; CHARGE UEB APA ACCOUNT $165.00
04/03/2018 BUILDING PRE-SLAB Partial Approval POST TENSION CABLE SYSTEM AT GARAGE LEVEL #1, PART C; 146 UNIFORM TENDONS; 109 BANDED TENDONS; 160 HAIRPINS. OK TO PLACE CONCRETE.
03/25/2018 BUILDING PRE-SLAB Partial Approval POST TENSION CABLE SYSTEM: GARAGE, LEVEL #1, PARKING ;DECK AT GL: 11/N-S; S/11-8.3; 8.3/S-X; X/8.3-1.5; 1.5/N-X; N/1.5-11. OK TO PLACE CONCRETE. (198 CABLES - 348 HAIRPINS)
03/23/2018 BUILDING PRE-SLAB Partial Approval BUILDING #1, MOISTURE BARRIER AND WIRE MESH RE-ENFORCEMENT: GL: A-G/14-17. OK TO PLACE CONCRETE. AFTER HOURS INSPECTION: CHARGE $165 TO "APA" ACCOUNT.
03/12/2018 BUILDING PRE-SLAB Partial Approval GARAGE: PART "C" AT GL: 13 - 17/N - T; 8.5 - 17/T - Y. OK TO PLACE CONCRETE IN PROGRESS AREAS.
03/08/2018 BUILDING PRE-SLAB Partial Approval VAPOR BARRIER/WIRE MESH REINFORCING SYSTEM AT GL: N - Y/1.5 - 13. OK TO PLACE CONCRETE IN PROGRESS AREAS. THIS INSPECTION WAS PREVIOUSLY COMPLETED ON 6 MAR 18.