Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T17CM03902
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/28/2018 | EXCAVATION/LAYOUT REBAR & ZON | Approved | Vapor mitigating System in place; #4 wire mesh reinforcement; Ok to place concrete | |
08/24/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | BUILDING #1, (FOOTINGS) AT GL: 14-17/G-N. OK TO PLACE CONCRETE. | |
07/23/2018 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | CONTRACTOR CANCELLED. | |
05/09/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | BUILDING: GARAGE/COURTYARD FOOTINS: WF-1 AND WF-3 AT GL: M.5/9 - 13. OK TO PLACE CONCRETE. | |
05/08/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMNS ON LEVEL #3, SECTION "C" 1 @ CC13 AT GL: 12/T; 1 CC18 AT GL: 12/U. OK TO PLACE CONCRETE. | |
04/17/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | INSPECTION PERFORMED ON PERMIT # T17CM04612 | |
04/16/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | BUILDING #3: GRADE BEAMS (GB-1) AT GL: Y-Z/7-17; WF 1 AT GL: Z/5-17; WF2 AT GL: W-Y/15.5-17; WF2 AT GL: Y-Z/1-3. OK TO PLACE CONCRETE. NOTE: AFTER HOURS INSPECTION ON THIS DATE. PLEASE CHARGE UEB "APA"ACCOUNT $165.00 APPROVED BY KEVIN DUNN |
|
04/13/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | GARAGE: COLUMNS: LEVEL #2, SECTION "B", 2 @ CC11 AT GL: U/4.5-8; 1 @ CC11 AT GL: T/10.4; 1 @ CC12 AT GL: U/10.4; 2 @ CC13 AT W-Y/10.4; 1 @GL: W/6; 1 @ CC13 AT GL: W/8. OK TO PLACE CONCRETE. | |
04/12/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SHEAR WALL #5, GL: N/7-9; LEVEL #2 TO LEVEL #3;; COLUMNS: GARAGE; LEVEL #2, SECTION "C"; 6 @ CC15 AT GL: 1.5/N-W; 2 @ CC20 AT GL: N-O/2.4; 1 @ CC11 AT GL: Q/2.4; 1 @ CC16 AT GL: T/2.4; 1 @ CC11 AT GL: V/2.4; 2 @ CC11 AT GL: R-T/4.5; 1 @ CC11 AT GL: T/8; 1 @ CC 13 AT GLl V/8. OK TO PLACE CONCRETE. | |
04/11/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMNS: BUILDING #2, 5 @ CC1 AT GL: L/7-12; 1 @ CC4 AT GL: L/2; 1 @ CC1 AT GL: M/3.5. OK TO PLACE CONCRETE. | |
04/11/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | GARAGE: LEVEL #2, SECTION "C" - COLUMNS: 3 # CC11 AT GL: 4.5-10.5/S; 2 # CC12 AT GL: 8-10.5/R; 4 @CC12 AT GL: 3-6/N-O; 3 @ CC19 AT GL: 9/O; 1 @ CC17 AT GL: 10/O; 1 @ CC11 AT GL: 10/N. OK TO PLACE CONCRETE IN PROGRESS AREAS. | |
04/09/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FOOTINGS: 3 @F2; 1 @ F5; 1 @F4; 1 @F1 AT GL: L/1 - 12.1; F3 AT M/3.5; WALL FOOTING AT K-M/1-12.1. OK TO PLACE CONCRETE. | |
04/07/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | GARAGE: LEVEL #1 TO LEVEL #2; SHEAR WALL #5 AT GL: W-Y/15.3. COLUMNS: LEVEL #1, PART "C"; 3 @ CC11 AT GL: 14/U-Y; 4 @ CC11 AT GL: 13/T-Y. OK TO PLACE CONCRETE IN PROGRESS AREAS. NOTE: AFTER HOURS INSPECTION ON THIS DATE CHARGED UEB APA ACCOUNT $165, APPROVED BY KEVIN DUNN. |
|
04/06/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | GARAGE, SHEAR WALL #5, LEVEL #1 - 2; COLUMNS: 6 @CC1, 3 @ CC13; 1 @ CC18; KLEVEL #1, PART "C" GL: 17/O-W; 12/T-W.9; 15.8/W.9; 14-15/T. BUILDING #1, FOOTINGS AT GL: L-N/14-17. OK TO PLACE CONCRETE IN PROGRESS AERAS. | |
04/05/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SHEAR WALL #7, AT GL: 12/R-T (LEVELS #1 AND #2); FOOTINGS IN BUILDING #1 AT GL: G-L/14-17; COLUMNS: 1 @ CC11 AT V.9/16; 3 @ CC11 AT GL: U/15 - 17; 1 @ CC11 AT P/17; 3 @ CC11 AT GL: R.4/16;. OK TO PLACE CONCRETE IN PROGRESS AREAS. | |
04/04/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | GARAGE; LEVEL #1, SECTION "C": 14 COLUMNS AT 3 @ CC11 ON GL: N/11.9-13; 3 @ AT GL: O/11.8-14; 3 @ CC11 AT GL: R/13 - 15; 3 @ CC11 AT GL: S/13- 15; 2 @ CC11 AT GL: N/15-16. OK TO PLACE CONCRETE. | |
04/03/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | BUILDING (GARAGE) SHEAR WALL #10 AT GL: N/7-9, LEVEL #1 TO LEVEL #2. OK TO PLACE CONCRETE. | |
03/29/2018 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | CONTRACTOR CANCELLED. | |
03/28/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | PARKING GARAGE: COLUMNS; LEVEL #1, CC12 AT W/6; CC11 AT U/4.5; CC11 AT S/10.4; CC11 AT R/4.5; CC11 AT Q/2.4; CC12 AT O/6; CC17 AT 0/10; CC11 AT N/10; CC12 AT N/6; CC12 AT N/3; CC20 AT N/2.4. OK TO PLACE CONCRETE. | |
03/27/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | PARKING GARAGE: COLUMNS AT 6 @ CC15 AT GL: 1.5/N-W; CC16 AT 2.4/5; 2 @ CC11 AT GL: 4.5- 8.1/S; CC19 AT GL: 9/O; CC11 AT GL: 2.3/V; 2 @ CC13 AT 8.1/W- W.9; CC11 AT 8.1/T.9. OK TO PLACE CONCRETE. | |
03/08/2018 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | CONTRACTOR CANCELLED. | |
03/06/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | BUILDING #1, VAPOR BARRIER/WIRE MESH REINFORCING SYSTEM AT GL: N-Y/1.5-13. OK TO PLACE CONCRETE IN PROGRESS AREAS. | |
03/01/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SHEAR WALL #14 AT LEVEL 1 UP TO LEVEL #2: GL: Y/1.5-4; CONCRETE WALL AT GL: Z/4-6. OK TO PLACE CONCRETE IN PROGRESS AREAS. | |
02/28/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMNS: 1 @ CC6 AT GL: Z/4; SHEAR WALL #13; TO LEVEL #1. | |
02/26/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SCHEDULING INFORMATION | |
02/23/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | STAIR FOOTINGS AT GL: 1.5 - 5/Y - Z; FOOTING F-3 AT GL: Z/4; SHEAR WALL #13 AT GL: Y.5 - Z/2.4 - 3. OK TO PLACE CONCRETE. | |
02/23/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | ||
02/23/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | STAIR FOOTINGS AT GL: 1.5 - 5/Y - Z, FOOTING F-3 AT GL: Z/4; SHEAR WALL #13 FOOTING AT GL: Y.5 - Z/2.4 - 3. OK TO PLACE CONCRETE. | |
02/22/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | BUILDING #1, FOOTINGS AT GL: G - A/14 -17. OK TO PLACE CONCRETE IN PROGRESS AREAS. | |
02/20/2018 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | CONTRACTOR CANCELLED. | |
02/16/2018 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | rain day | |
02/15/2018 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | CONTRACTOR CANCELLED - RAINED OUT. | |
02/14/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SHEAR WALLS: SW-12; LEVEL #1 TO LEVEL #2 (12'). OK TO PLACE CONCRETE | |
02/13/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | INFORMATION ONLY (SHEAR WALLS) | |
02/12/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMNS: CC-6 AT B.5/9; CC-1 AT H.2/11' CC-1 AT H/12; 2 @ CC-1 AT I - K/12; CC-11 AT T/10.4; CC-13 AT W.9/12; 2 @ CC-13 AT W - W.9/10.4. CONCRETE WALLS: CW-1 AND CW-2 AT 17.2/M.8 - Q.5; CW-1 AND CW -2 AT 13.9 - 17/M.8; CW-2 AT 1.4/N - Q.5. OK TO PLACE CONCRETE. | |
02/07/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FOOTINGS: F-1 @ H.2/11; F-5 @ H/12; F-3 @ I/12.1; F-3 @ K/12.1. OK TO PLACE CONCRETE. | |
02/06/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SHEAR WALL - 4 AT GL: J/8.5 - 10. COLUMNS: 2 @ CC-18 AT 12/T -U; 1 @ CC-13 AT W/12. | |
02/05/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMNS: CC-6 @ A.8/9; CC-10 @K.3/4; CC-1 @ J/11. OK TO PLACE CONCRETE. | |
02/02/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | BUILDING #2: FOOTINGS : F-1 @ K.5/4/ SHEAR WALL MAT FOOTING AT GL: J/8.2 - 11.2; COLUMNS: CC-1 @ H.4/8.5; CC-2 @ H.4/3; CC-4 @ H.2/2; 4 EACH CC-5 AT H - L/1. OK TO PLACE CONCRETE. | |
02/01/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMNS: CC-8 @F/4.2; CC-1 @ G.5/3.5; CC-1 @ H.5/7; CC-1 AT J/6; CC-9 @ J/2; CC-1 @ H.8/4: CONCRETE WALLS: CW-1 AT Q.5 - W/17; CW-1 @ N/5 - 13.9; CW - 1 @ W - Y/15.8; CW-1 @ W/15.8 - 17. OK TO PLACE CONCRETE | |
01/31/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FOOTINGS: F-4 2 GL: A.8/9, F-5 @ GL: B.5/9; 3 @ F-5, 1 @ F-4 AT GL: H - L/1, F-3 @ H.2/2; F-3 @ H.4/3, F-1 @ J/2; F-1 @ J/6, F-1 @ H.6/7, F-2 @ H.4/8.5. COLUMNS: 2 @ CC-3 @ D-F/1; 2 @ CC-2 AT C.4/2, E.8/2, CC-7 @ D.3/2. OK TO PLACE CONCRETE. | |
01/30/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | BUILDING #2: FOOTINGS: 2 @ F-2, 2 @ F-3, 1 @ F-1, 1 @F-5 AT GL: D - F/1 - 4.5; 1 @F-2 AT GL: G.5/3.5; 1 @ F - 1 AT H.6/4. COLUMNS: 1 @ CC3 AT GL: C/1, CC3 AT E/1, CC1 AT C.6/4, 1 CC1 AT E/3.5. CONCRETE WALLS : CW-1 @ Y - Y.3/3 - 6, CORNER OF WALL AT GL: M-M.8/1.4. OK TO PLACE CONCRETE IN PROGRESS AREAS. | |
01/26/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | GARAGE: CONCRETE WALL - 1 AT GL: N/1.5 - 5; BUILDING #2: SHEAR WALL -1 AT GRADE LEVEL TO LEVEL #2; SHEAR WALL - 3: GRADE LEVEL TO LEVEL #2. FOOTINGS: F -1 AT C.6/4; F - 2 AT C.4/2; 2 @ F - 5, 1 @ F - 4 AT GL: 1/C - E; WALL FOOTING @ C/3.5 TO F -1. COLUMNS : 2 @ CC1 AT H.4/10; 7/B.5 - D; 1 @ CC1 AT 6/D.8; 1 @ G/9; 1 @ CC1 AT H.4/10. OK TO PLACE CONCRETE IN PROGRESS AREAS. | |
01/25/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | BUILDING #2: CONCRETE WALL - 1 AT GL: Y/1.5 - 4.5; Y/8.5 - 15.7; PILASTER AT SHEAR WALL #2, GL: D.8/6. OK TO PLACE CONCRETE. | |
01/24/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | BUILDING #2: MATS (2) AT SHEAR WALL #3 AND SHEAR WALL- #1: FOOTINGS: CC-1 AT B/7; COLUMNS: 3 @ CC-3 AT A.3/3 - 9; CC-3 AT A.4/5; CC-4A AT A.5/7.5; CC-2 AT B/6; CC-3 AT B.3.5; 3 @ CC-1 AT B.5 - C.5/8 - 10; CC-1 AT F/9. OK TO PLACE CONCRETE. | |
01/23/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | BUILDING #2: FOOTINGS: F-1 AT GL: D/7; F-2, F-3, F-2 AT GL: E.5 - H.4/9; FOOTINGS: 3 @ F-5 AT GL: A.3/3 -9; F-4 AT GL: A.5/5; F-5 AT A.8/7.5. 2 @ F-5 AT GL: B/3.5 - 6; ALL WF-1 CONNECTING COLUMN FOOTINGS. COLUMNS: 1 @ CC1 AT E/10; 7 @ CC1 AT GL: C - F/11 - 12.1; SHEAR WALL -1; GRADE LEVEL TO LEVEL 2. GARAGE: CW -1 AT Y/4.7 - 8.5. OK TO PLACE CONCRETE IN PROGRESS AREAS. | |
01/22/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FOOTINGSS: F-4, AT GL: O/16; F-13 AT GL|: 0/17; WF-2 AT GL: 17/N - O.5; WF-2 AT GL: N/16 - 17; WF-1 AT GL: Y.2/3 - 6. CONCRETE WALL -1 AT GL: 1.4/Q.5 - Y; CONCRETE WALL-2 AT GL: 1.3/N - Q.5. OK TO PLACE CONCRETE IN PROGRESS AREAS. | |
01/19/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMNS: 2 @ CC11, GL: N/15 - 16; 1 @ BARRIER WALL AT GL: T/12 - 15; SW - 14 AT GL: Y/1.5 - 3.5; BUILDING #2; FOOTINGS ( 7 ) AT GL: C - F/10.4 - `12.1; F - 1 AT D.8/10; F12 AT C.2/8.5; F-4 AT B.8/9; F-3 AT C.2/10. OK TO PLACE CONCRETE | |
01/18/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | MAT FOOTING: D.5 - E.5/7 - 8.5; F-2 FOOTING AT D.8/6. OK TO PLACE CONCRETE. | |
01/17/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | PILASTERS: 1 @ W.9/10.4; 3 @ T - W.9/12; COLUMNS : CC13 AT W.9/8.1; 3 @ CC11 AT N/11.8 - 13.9; SHEAR WALLS: SW - 5 BOTTOM OF DECK OF WALL AT LEVEL #1; SW-10, LEVEL #1 DECK BOTTOM; SW - 12 BOTTOM OF LEVEL #1 DECK. OK TO PLACE CONCRETE IN PROGRESS AREAS. | |
01/16/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | CONCRETE WALL #3 AT GL: 8.5/T - W; 8" BARRIER WALL AT 4.5 - 8/T; SW -6: 15.2/W - X; WF-2 AT 14 - 15/N; MAT FOOTING AT 14.8 - 15.8/N - P; WF-2 AT 7 - 8.5/W.9; WF-2 AT 1.5/W.5 - W.9; F-5 8.1/W.9. OK TO PLACE CONCRETE IN PROGRESS AREAS. | |
01/11/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMNS 1 @ CC11 AT N/10; 1 @ CC17 AT O/10; 1 @ CC13 AT W/8.1; 1 @ CC18 AT R.5/12; 1@ CC11 AT R/14; 2 @ CC11 AT R - T/15; 4 @ CC11 AT P - W/16; 1 @ CC11 AT V.8/17. OK TO PLACE CONCRETE IN PROGRESS AREAS. | |
01/09/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMN FOOTINGS: 2 @ F-10 GL: R/13, R/14, R/15; 1 # F-9 @ R/16, MAT FOOTING AT SW6 @ MAT FOOTING @ V.5/17-16, WR-1 AT W - W.5/15.5-16; COLUMNS AT GL: O - W/ 12.9 - 17 14 AT CC11; CC11 a V/2.4, CC19 @ O/9; 5 @ (2 @ CC12, 1 @ CC1, 1 @ CC20, 1 @ CC15) N/1.5 -6. OK TO PLACE CONCRETE IN PROGRESS AREAS | |
01/08/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | WALL FOOTINGS: GL: (WF-2) N/14 - 10.5, N/5 - 1.5; EAST WALL (WF-2) GL: W.9/8.5 - 15; COLUMNS 3 @ F - 13; GL; N/13.9, N/12.9, N/11.8; F-13 AT N/3.5; 2 @ F-12, N/2.4, N/1.5, 4 @ F-5; W.9/14; W.913, W.9/12, W.9/10.4. COLUMNS: 2 @ CC1 AT GL: N/7, N/9: CC11 AT O/11.8. OK TO PLACE CONCRETE. | |
01/05/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMN FOOTING : F-3 AT 16/P; 3 PILASTERS AT GL: 10.4/T - W. OK TO PLACE CONCRETE. | |
01/04/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMN FOOTINGS: F-9 AT 13.9/O; F-10 AT 16/U; F-14(3) AT 17/P - U; F-4 AT 15/S - T; WALL FOOTING (WF-1) AT T/12 - 15; WF-2 A 17/O.5 - V.5. COLUMNS: GL: O/1.5 - 6 (3), (1) AT Q/1.5; 3 AT R/4.5 -10.5; 3 AT S/4.5 -10.5; 2 ATT/4.5 - 8.1; 2 AT T.9/4.5 - 8.1; 1 AT W/6. OK TO PLACE CONCRETE AT PROGRESS AREAS. | |
01/03/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMN FOOTINGS T GL: F-10 AT 15/U; F-11 AT 14/R; F-9 AT 12.9/O; F-5 AT 11.8/0. OK TO PLACE CONCRETE. | |
01/02/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMNS CC15 (3) AT GL: 1.5/S - W; CC11 AT GL: Q/2.4; CC20 AT GL: 2.2/O. FOOTINGS F-4 AT GL: 14/S - T, F.11, F-10 AT GL: 14/W - U; SW11 A AND B AT GL: W - Y/4.74 - 3. OK TO PLACE CONCRETE IN PROGRESS AREAS. | |
12/29/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMN FOOTINGS AT F-5 (W/12), F-7 (U/13), F-10 (13/W), STAIRWELL #7, COLUMN #CC16. OK TO PLACE CONCRETE. | |
12/28/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | WALL FOOTINGS #2 AT GL: N - Y/1.25; SPREAD FOOTINGS SOUTH OF GL: 11.8/N - Y; WALL FOOTING #1 AT GL: T/8 - 11.8; CW3 AT GL: 8/T - V. FOOTINGS OF F-1 TO F-13: OK TO PLACE CONCRETE IN PROGRESS AREAS. | |
12/18/2017 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | CONTRACTOR CANCELLED - RAINED OUT. | |
12/14/2017 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | CONTRACTOR CANCELLED | |
12/13/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | WALL FOOTINGS AT GL: 1.5/Q.5 - W.5: WF2, CC12 (2), CC6 (1), DETAILS #114, 114. WALL FOOTINGS/ SPREAD FOOTINGS AT GL: Y/8.1 - 14.2, WF1, WF2, CC6 (2), CC 8 (2); DETAILS #113, 114, OK TO PLACE CONCRETE IN PROGRESS AREAS. | |
12/12/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FOUNDATION FOOTINGS AT GL: N - Q/10.4, N/4.75 - 10, 4.75/N - Q; Q/4.75 - 10. CONCRFETE COLUMN FOOTINGS: CC1 (1), CC7 (2), CC11 (1), CC15 (1). FOOTING (PAD) SW7; GL: 12.1/Q - U, 12.1 - 11.8/Q; 11.8/Q - U; U/11.8 - 12; SW7. OK TO PLACE CONCRETE FOR PADS AND CONCRETE COLUMNS. | |
12/08/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | BUILDING #3, PSRT "B": SLABS/FOOTINGS AT GL: V.9 -Z/7 - 1.5. SHEAR WALL FOOTINGS, SW 11A, SW11, SW11B, SW12. SUMP PIT LOCATED AS PER ARCHITECTURAL REQUEST. OK TO PLACE CONCRETE. | |
11/22/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | OVER-HEAD CRANE PAD FOOTING: AS PER REVISED PLANS DATED 11 - 21- 17. OK TO PLACE CONCRETE | |
11/07/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | INFORMATION ONLY. NEED COPIES OF ALL PREVIOUS SPECIAL INSPECTION REPORTS. |