Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
| Date |
Description |
Inspector |
Results |
Comments |
| 10/02/2019 |
BUILDING - PROGRESS |
|
Approved |
|
| 02/13/2019 |
BUILDING - PROGRESS |
|
Partial Approval |
2 bbq slab, fog, steel between bldg 6 and 7 |
| 01/23/2019 |
BUILDING - PROGRESS |
|
Partial Approval |
Masonry columns pre-grout for stair columns to 16’. |
| 01/15/2019 |
BUILDING - PROGRESS |
|
Partial Approval |
Pre-grout for stairway columns to 12 feet |
| 01/09/2019 |
BUILDING - PROGRESS |
|
Partial Approval |
Stair support columns pre grout first eight feet. |
| 11/29/2018 |
BUILDING - PROGRESS |
|
Partial Approval |
|
| 11/08/2018 |
BUILDING - PROGRESS |
|
Partial Approval |
STAIRCASE FOOTINGS OK TO GROUT |
| 03/09/2018 |
BUILDING - PROGRESS |
|
Partial Approval |
PRE CONSTRUCTION MEETING |