Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 12/10/2019 |
ENGINEERING - FINAL |
|
Approved |
|
| 11/01/2019 |
ENGINEERING - FINAL |
|
Partial Approval |
OK for TCO per Ron Ledonne. |
| 10/28/2019 |
ENGINEERING - FINAL |
|
Not ready for Inspection |
Complete all work on development package. Provide certification letter and as Builts for all grading and drainage. Repair ADA parking that is over 2% on north side of building six and seven. Provide repairs and revision for sidewalk on west side of maintenance building. |