Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date |
Description |
Inspector |
Results |
Comments |
| 03/04/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Approved |
Stair columns complete |
| 02/21/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
3rd lift of masonry. |
| 02/14/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Second lift at stair columns. Approved second lift, line open for third lift. |
| 02/13/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
2 bbq pits, footing, steel, conduit .for slab pour |
| 02/11/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
6 Stair pads, 12” thick with rebar. 10- 8’ high columns for stairs, rebar, OK for 8’ grout pour with clean outs in place. |
| 02/04/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Ftgs & steel for staircases on this bldg. |
| 11/29/2018 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
|