Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
Permit Number - T17CM03785
Inspection Description - BUILDING - PROGRESS
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/10/2019 | BUILDING - PROGRESS | Approved | ||
| 11/08/2018 | BUILDING - PROGRESS | Partial Approval | BUILDING 1 OK TO GROUT UP TO 8' MAIL AND GAZEBO | |
| 10/31/2018 | BUILDING - PROGRESS | Partial Approval | Mailbox and adjacent structure ok to grout 1st lifts | |
| 10/15/2018 | BUILDING - PROGRESS | Not ready for Inspection | First floor trusses not ready | |
| 09/18/2018 | BUILDING - PROGRESS | Partial Approval | PRE-GROUT FOR BLDG 1 STAIRS - W. COLUMNS OK TO 12', N.W. 1 COLUMN OK TO 16' AND 3 OTHER N. COLUMNS OK TO TOP. S. + E. COLUMNS OK TO 20' | |
| 09/13/2018 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 09/11/2018 | BUILDING - PROGRESS | Partial Approval | STAIRCASE TOWERS NW-2 COLUMNS 12' NE-2 COLUMNS 16' E-2 COLUMNS 16' W-2 COLUMNS 12' ALL COLUMNS WITH #5 |
|
| 09/11/2018 | BUILDING - PROGRESS | Partial Approval | detailed list left on site | |
| 09/05/2018 | BUILDING - PROGRESS | Partial Approval | ALL STAIR COLUMNS OK TO GROUT 3RD LIFT | |
| 03/09/2018 | BUILDING - PROGRESS | Partial Approval | PRE CONSTRUCTION MEETING |