Inspection Status: Approved
Inspection History: FRAMING
| Date |
Description |
Inspector |
Results |
Comments |
| 03/04/2019 |
FRAMING |
|
Approved |
First floor is now done as was second and third floor |
| 03/01/2019 |
FRAMING |
|
Cancelled |
Per phone call from customer. |
| 02/25/2019 |
FRAMING |
|
Partial Approval |
|
| 02/15/2019 |
FRAMING |
|
Partial Approval |
3rd floor only |
| 11/05/2018 |
FRAMING |
|
Partial Approval |
couple spots missing Nails on Northwest side. Third floor deck okay to start framing on top of. |
| 10/16/2018 |
FRAMING |
|
Not ready for Inspection |
Finish south side floor decking and recall |
| 10/12/2018 |
FRAMING |
|
Cancelled |
Too slippery with rain to perform safe inspection |