Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/23/2017 | PLUMBING - GAS PRESSURE TEST | Approved | ||
| 05/18/2017 | PLUMBING - GAS PRESSURE TEST | Denied | 1- SEE NOTES #1,2,3 FROM THR PREVIOUS INSPECTION ON 05/11/17. 2- SHALL PROVIDE AN APPROVED DRAWING FOR THE NEW GAS LINE SYSTEM SHOWING FULL DEVELOPED LENGTH OF THE PIPING AND BTU TO CFH DEMAND. |
|
| 05/11/2017 | PLUMBING - GAS PRESSURE TEST | Denied | 1- SHALL PROVIDE THE APPROVED DRAWINGS AND PERMIT ON SITE AT THE TIME OF INSPECTION. 2- SHALL EXTEND THE T & p DRAIN AND PROVIDE A WATER HEATER DRIP PAN AND CAP THE OUTLET AND TERMINATE THE T & P DRAIN INTO THE PAN. 3- SHALL SECURE THE GAS DROP INTO THE KITCHEN. 4- SHALL PROVIDE A SEDIMENT TRAP AT THE WATER HEATER. 5- PROVIDE ACCESS TO THE ROOF. |