Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - SEWER HCS CONNECT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/16/2017 | PLUMBING - SEWER HCS CONNECT | Approved | ||
| 10/03/2017 | PLUMBING - SEWER HCS CONNECT | Partial Approval | IVRS - Inspection :* 1- SITE SEWER FROM THE PARTIAL APPROVAL LOCATION OF PREVIOUS INSPECTION TO CONTINUOUS PIPING AS NOTED ON PLAN IS OKAY TO COVER, WATER TEST PROVIDED. 2- SHALL PROVIDE AN APPROVED REVISED PLAN SHOWING THE RELOCATION OF THE SITE SEWER PRIOR TO FINAL INSPECTION. |
|
| 09/18/2017 | PLUMBING - SEWER HCS CONNECT | Partial Approval | OK TO BACKFILL SITE SEWER FROM HCS TO 85' NORTH AND TO 40' WEST. STILL NEED TO SEE CONNECTIONS TO SITE SEWER. | |
| 09/15/2017 | PLUMBING - SEWER HCS CONNECT | Partial Approval | IVRS - Inspection :* |