Permit: T17CM03527

Parcel: 136092160

Inspection Status: Approved

Inspection History: BUILDING - FINAL

Date Description Inspector Results Comments
06/20/2018 BUILDING - FINAL Approved
05/30/2018 BUILDING - FINAL Partial Approval OK FOR SALES OFFICE TO BE INSPECTED FOR FINALS
08/04/2017 BUILDING - FINAL Not ready for Inspection IVRS - Inspection :*
08/03/2017 BUILDING - FINAL Partial Approval IVRS - Inspection :*
07/21/2017 BUILDING - FINAL Partial Approval app pending engineering
07/20/2017 BUILDING - FINAL Not ready for Inspection IVRS - Inspection :*
07/20/2017 BUILDING - FINAL Not ready for Inspection Proide required paperwork for final.
Backflow prevention assembly requires a certification test.
Backflow prevention assembly requires freeze protection.
Correct the slope of FAU vent connector.
Seal and protect line set insulation. Condensate leaking fom overflow