Inspection History Details
Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
Permit Number - T17CM03376
Inspection Description - REINFORCED MASONRY PRE-GROUT
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/12/2019 | REINFORCED MASONRY PRE-GROUT | Approved | per Matt Ramber | |
05/24/2018 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | No Access Gate Locked at 4pm | |
05/22/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | TOP OUT GL 4 FROM B-B10 4TH FLOOR PENDING SI REPORT |
|
05/18/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 8' LIFT WITH WEEPS 4TH FLOOR GL 4 FROM B-B.10 PENDING SI REPORT | |
04/13/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | west stairwell interior walls ok | |
04/05/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | service elevator top out ok pending S.I. report storage room east stairwell ok to top out |
|
03/29/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | service elevator pit ok Special Inspection Cert for A.7 and B.05 | |
03/28/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | lift ok pending S.I. report | |
03/22/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | GL-1 to 2.5 and service elevator 17th lift ok pending S.I. report | |
03/19/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 14th lift at stairwell ok pending S.I. report | |
03/15/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 16th lift CL 1 to 2.5 pending SI report | |
03/13/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 16th lift service elevator, 15th lift at CL 1 thru 2.5 ok pending S.I. report | |
03/07/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 14th lift C.L. 1 to 2.5 15th lift service elevator pending S.I. report |
|
03/02/2018 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | no work | |
03/01/2018 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | cancelled | |
02/23/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | top out south wall2.5 to 4.5. service elevator 14th lift. G.L. 1 to 2.5 13th lift . pending S.I. report | |
02/21/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 13th lift east stairwell,public elevator, south wall at CL 1 to 2.5 ok pending S.I. report | |
02/14/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 12th lift C.L. 2.5 to 6 including service elevator 11th lift C.L. 1 to 2.5 |
|
02/09/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 10th lift at CL 1 to 2.5, 11th lift at CL 2.5 to 6 and service elevator | |
01/30/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 8th lift east staitwell to G.L. 2.5 pending S.I. report | |
01/29/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 8TH LIFT 2.5 WEST OKAY | |
01/24/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 7TH LIFT OK TO POUR | |
01/22/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 6TH LIFT APPROVED | |
01/17/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
01/16/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 5th lift tower and south wall up to C.L. 2.8 | |
01/09/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | KITCHEN AREA WALLS 4TH LIFT ROOM 128 4TH KIFT WEST WALL FIRE PUMP BOOSTER ROOM 127 4TH LIFT WEST STAIRWELL ROOM 125 |
|
01/08/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 4TH LIFT EAST STAIRWAY 4TH LIFT EAST ELEVATOR |
|
01/04/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | south outer wall 4th lift ok up to west elevator 3rd lift west elevator and south west walls ok |
|
12/29/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | public elevator above lintel, west wall 2nd lift south wall 3rd lift ok | |
12/15/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 3rd lift east stair and south wall east, 2nd lift south wall west and west stair | |
12/12/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 2nd lift east stair/south wall ok 1st lift elevators and west walls ok |
|
12/11/2017 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | no work | |
12/01/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | east stairwell 1st lift ok, south wall 1`st lift ok |
|
11/30/2017 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | no work | |
10/23/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | public elevator pit ok |