Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T17CM03376

Parcel: 117131560


Addresses:

192 S STONE AV


Inspection Status: Approved

Inspection History: REINFORCED MASONRY PRE-GROUT

Permit Number - T17CM03376

Inspection Description - REINFORCED MASONRY PRE-GROUT

Inspection Status - Approved

Date Description Inspector Results Comments
03/12/2019 REINFORCED MASONRY PRE-GROUT Approved per Matt Ramber
05/24/2018 REINFORCED MASONRY PRE-GROUT Not ready for Inspection No Access Gate Locked at 4pm
05/22/2018 REINFORCED MASONRY PRE-GROUT Partial Approval TOP OUT GL 4 FROM B-B10 4TH FLOOR
PENDING SI REPORT
05/18/2018 REINFORCED MASONRY PRE-GROUT Partial Approval 8' LIFT WITH WEEPS 4TH FLOOR GL 4 FROM B-B.10 PENDING SI REPORT
04/13/2018 REINFORCED MASONRY PRE-GROUT Partial Approval west stairwell interior walls ok
04/05/2018 REINFORCED MASONRY PRE-GROUT Partial Approval service elevator top out ok pending S.I. report
storage room east stairwell ok to top out
03/29/2018 REINFORCED MASONRY PRE-GROUT Partial Approval service elevator pit ok Special Inspection Cert for A.7 and B.05
03/28/2018 REINFORCED MASONRY PRE-GROUT Partial Approval lift ok pending S.I. report
03/22/2018 REINFORCED MASONRY PRE-GROUT Partial Approval GL-1 to 2.5 and service elevator 17th lift ok pending S.I. report
03/19/2018 REINFORCED MASONRY PRE-GROUT Partial Approval 14th lift at stairwell ok pending S.I. report
03/15/2018 REINFORCED MASONRY PRE-GROUT Partial Approval 16th lift CL 1 to 2.5 pending SI report
03/13/2018 REINFORCED MASONRY PRE-GROUT Partial Approval 16th lift service elevator, 15th lift at CL 1 thru 2.5 ok pending S.I. report
03/07/2018 REINFORCED MASONRY PRE-GROUT Partial Approval 14th lift C.L. 1 to 2.5
15th lift service elevator pending S.I. report
03/02/2018 REINFORCED MASONRY PRE-GROUT Not ready for Inspection no work
03/01/2018 REINFORCED MASONRY PRE-GROUT Not ready for Inspection cancelled
02/23/2018 REINFORCED MASONRY PRE-GROUT Partial Approval top out south wall2.5 to 4.5. service elevator 14th lift. G.L. 1 to 2.5 13th lift . pending S.I. report
02/21/2018 REINFORCED MASONRY PRE-GROUT Partial Approval 13th lift east stairwell,public elevator, south wall at CL 1 to 2.5 ok pending S.I. report
02/14/2018 REINFORCED MASONRY PRE-GROUT Partial Approval 12th lift C.L. 2.5 to 6 including service elevator
11th lift C.L. 1 to 2.5
02/09/2018 REINFORCED MASONRY PRE-GROUT Partial Approval 10th lift at CL 1 to 2.5, 11th lift at CL 2.5 to 6 and service elevator
01/30/2018 REINFORCED MASONRY PRE-GROUT Partial Approval 8th lift east staitwell to G.L. 2.5 pending S.I. report
01/29/2018 REINFORCED MASONRY PRE-GROUT Partial Approval 8TH LIFT 2.5 WEST OKAY
01/24/2018 REINFORCED MASONRY PRE-GROUT Partial Approval 7TH LIFT OK TO POUR
01/22/2018 REINFORCED MASONRY PRE-GROUT Partial Approval 6TH LIFT APPROVED
01/17/2018 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
01/16/2018 REINFORCED MASONRY PRE-GROUT Partial Approval 5th lift tower and south wall up to C.L. 2.8
01/09/2018 REINFORCED MASONRY PRE-GROUT Partial Approval KITCHEN AREA WALLS 4TH LIFT ROOM 128
4TH KIFT WEST WALL FIRE PUMP BOOSTER ROOM 127
4TH LIFT WEST STAIRWELL ROOM 125
01/08/2018 REINFORCED MASONRY PRE-GROUT Partial Approval 4TH LIFT EAST STAIRWAY
4TH LIFT EAST ELEVATOR
01/04/2018 REINFORCED MASONRY PRE-GROUT Partial Approval south outer wall 4th lift ok up to west elevator
3rd lift west elevator and south west walls ok
12/29/2017 REINFORCED MASONRY PRE-GROUT Partial Approval public elevator above lintel, west wall 2nd lift south wall 3rd lift ok
12/15/2017 REINFORCED MASONRY PRE-GROUT Partial Approval 3rd lift east stair and south wall east, 2nd lift south wall west and west stair
12/12/2017 REINFORCED MASONRY PRE-GROUT Partial Approval 2nd lift east stair/south wall ok
1st lift elevators and west walls ok
12/11/2017 REINFORCED MASONRY PRE-GROUT Not ready for Inspection no work
12/01/2017 REINFORCED MASONRY PRE-GROUT Partial Approval east stairwell 1st lift ok,
south wall 1`st lift ok
11/30/2017 REINFORCED MASONRY PRE-GROUT Not ready for Inspection no work
10/23/2017 REINFORCED MASONRY PRE-GROUT Partial Approval public elevator pit ok