Inspection Status: Approved
Inspection History: STEM WALL/RETAINING WALL
| Date |
Description |
Inspector |
Results |
Comments |
| 03/22/2019 |
STEM WALL/RETAINING WALL |
|
Approved |
no more stem retaining walls in job. This is to close out this inspection |
| 12/21/2018 |
STEM WALL/RETAINING WALL |
|
Partial Approval |
North of four story radius wall 6' per detail 107 |
| 12/14/2018 |
STEM WALL/RETAINING WALL |
|
Partial Approval |
Concrete forms wood Retaining walls rear of building |
| 11/15/2018 |
STEM WALL/RETAINING WALL |
|
Partial Approval |
Chapel vent ok. |
| 11/13/2018 |
STEM WALL/RETAINING WALL |
|
Partial Approval |
Chapel vent ok |
| 10/09/2018 |
STEM WALL/RETAINING WALL |
|
Partial Approval |
ADA ramp at marisch college ok |
| 09/21/2018 |
STEM WALL/RETAINING WALL |
|
Partial Approval |
entry columns ok |
| 08/15/2018 |
STEM WALL/RETAINING WALL |
|
Partial Approval |
west chapel stair wall ok |
| 01/16/2018 |
STEM WALL/RETAINING WALL |
|
Partial Approval |
radius and north stem ok |
| 01/11/2018 |
STEM WALL/RETAINING WALL |
|
Not ready for Inspection |
no work |
| 10/26/2017 |
STEM WALL/RETAINING WALL |
|
Partial Approval |
1010 STEM WALL TOPOUT LINE 1 A THRU D AND LINE B 1 THRU 3.4 |