Permit: T17CM03376

Parcel: 117131560


Addresses:

192 S STONE AV


Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T17CM03376

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
03/22/2019 EXCAVATION/LAYOUT REBAR & ZON Approved approval is for footings and slab for cage at front patio
03/12/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval pole bases at entry only
03/11/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Work not complete at pole bases
01/17/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Footings for site walls under stairs.
01/02/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Radius planters north at radius wall per detail 7/23
12/18/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval North radius retaining wall; East half.
11/15/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval North retaining wall, West 1/3 ok.
11/02/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Chapel vent wells ok.
10/26/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Radius wall north of Chapel ok.
10/23/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Radius wall north of Chapel footer ok
10/09/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval ADA ramp at marisch college ok
10/01/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval OK AT ENTRY STEPS
09/25/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval H.C. ramp footers ok.
08/08/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval N.E. retaining wall ok
07/30/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
07/05/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
SOUTH PLANTER WALL FOOTING PER DETAIL 7/23
06/20/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval caissons ok
02/05/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 9th lift from CL 1 to 2.5
10th lift from CL 2.5 to 6
pending S.I. report
11/08/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval elevator pit floors ok
11/06/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval stemwalls CL 3.5 to 5 along south wall
11/02/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval grade beam D/3.4 to D/4.4
10/31/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GRADE BEAMS AND CF1 AT STAIRWELL GRID LINE A &B FROM 4-6 ONLY
10/20/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval grade beams at CL 2 thru 4 on CL "B"
10/19/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection no work
10/17/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval grade beams area B thru D and 1 thru 2
10/16/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval elevator pits (2) at grade beams
10/13/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval caisson anchor bolts
10/09/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval caissons D/5 , C/5.4 , C.9/5.4
10/06/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval caissons F/3 , F/4 , G/S.1 , G/5.3 , F.5/S.1 , F.3/5.4
10/05/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval caissons B.3/2.2 , B.7/2.2 , B.2/2.4 , B.7/2.4 , C/3 , E/3 , C/4 , E/4 , H/1 , H/2 , H/3 , H/4 , S/1 , H/5 , H/5.5 ok
10/02/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval caissons B.4/5.4 , B/5.4 , A/4.8 , B/4.8 , B.6/4.8 , A/4.2 , B/4.2
09/29/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Caissons- B/6 , C/6 , B/4 , B/3.6 , B/3.2 , B/3 , C/1.4 , B.5/1.4 ok
09/28/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval caissons-F/1 , E.5/2 , C/2 , B/2 , B/2.2 , B/2.5 ok
cages-6 F6 cages ok
09/26/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CASONS
D.25-1 SEE HIGHLIGHTED CASONS ON S2.0

CAGES
CF-1 B/3, CF-1B6,CF-1 B/3E, CF-1 B/4W, CF-1 B4, CF-1 B6W, CFI 6/CS, CFI /H4.6, CFI/B5, CF-1/EL, CF-2/E4, CF-2 /E3, CF2/C3, CF-5/C4, CF-2/D5, CF-4/F1, CF-5/5, CF-5/A5, CF-5 B34, CF-5 53L, CF=5/ BW3, CF-5/A2, CF-5/2A, CF-1/ELSW, CF1/B4, CF-1 EL/SE, CF-1/ ELNW, CF-1/1.4L AND CF-1/F.6
09/25/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval FOUR COLUMNS HILIGHTED AND INITIALED WEN OK TO POUR.
09/22/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAGES: 4 - CF1, 5 - CF2, 6 - CF3, 7 - CF5 - ALL OK TO DROP
09/20/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval PARTIAL NUMBER OF CF-1, CF-2 & CF-3 CAGES