Inspection Status: Approved
Inspection History: FIRE SPKLR - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 09/19/2019 |
FIRE SPKLR - FINAL |
|
Approved |
|
| 06/07/2019 |
FIRE SPKLR - FINAL |
|
Partial Approval |
Phase 4 approved. |
| 12/14/2018 |
FIRE SPKLR - FINAL |
|
Partial Approval |
Phase 3 approved. |
| 11/15/2018 |
FIRE SPKLR - FINAL |
|
Cancelled |
IVRS - RI canceled |
| 11/15/2018 |
FIRE SPKLR - FINAL |
|
Partial Approval |
OK to hardlid basement pharmacy. |
| 08/08/2018 |
FIRE SPKLR - FINAL |
|
Partial Approval |
Phase #1 and #2 approved. Sprinkler inspection 1/2. More than two sprinkler inspections will result in reinspection fees. TCO approved for these phases. |
| 08/06/2018 |
FIRE SPKLR - FINAL |
|
Denied |
NOT READY. NOT CALLED IN PROPERLY WITH SUB CONTRACTOR FOR FIRE ALARM AND FIRE SPRINKLER> NEED TO LEAVE A MESSAGE WITH CONTACT INFORMATION ON THE HOTLINE. PAY REINSPECTION FEE PRIOR TO CALLING BACK IN> SEE L/H/N for comments |
| 07/13/2018 |
FIRE SPKLR - FINAL |
|
Not ready for Inspection |
SUPER NOT AVAILABLE |