Inspection Status: Partial Approval
Inspection History: MECHANICAL - ABOVE CEILING
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/13/2019 | MECHANICAL - ABOVE CEILING | Partial Approval | At fire damper breakaway, provide clips and remove corner bolts. | |
| 09/12/2019 | MECHANICAL - ABOVE CEILING | Cancelled | IVRS - AP canceled | |
| 06/03/2019 | MECHANICAL - ABOVE CEILING | Partial Approval | OK phase 4. | |
| 05/31/2019 | MECHANICAL - ABOVE CEILING | Cancelled | IVRS - AP canceled | |
| 05/23/2019 | MECHANICAL - ABOVE CEILING | Cancelled | IVRS - AP canceled | |
| 05/15/2019 | MECHANICAL - ABOVE CEILING | Partial Approval | Hard lids at phase 4 OK | |
| 05/14/2019 | MECHANICAL - ABOVE CEILING | Cancelled | IVRS - AP canceled | |
| 04/29/2019 | MECHANICAL - ABOVE CEILING | Partial Approval | Mechanical duct overhead. OK to insulate | |
| 04/25/2019 | MECHANICAL - ABOVE CEILING | Cancelled | IVRS - AP canceled | |
| 10/29/2018 | MECHANICAL - ABOVE CEILING | Partial Approval | Return duct in chase one OK to insulate. Ante garbling room supplies ok to insulate. Chemo hood room supply and return ok to insulate. Ante room supply and return ok to insulate. Transitional supply through I v Fluid room ok to insulate. | |
| 10/26/2018 | MECHANICAL - ABOVE CEILING | Cancelled | IVRS - AP canceled | |
| 08/06/2018 | MECHANICAL - ABOVE CEILING | Partial Approval | OK PHASE 1 | |
| 08/01/2018 | MECHANICAL - ABOVE CEILING | Approved | IVRS - Inspection :* | |
| 04/19/2018 | MECHANICAL - ABOVE CEILING | Partial Approval | Mechanical Ducting above Ceiling in Pharmacy | |
| 04/12/2018 | MECHANICAL - ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1- HVAC DUCT ABOVE CEILING IS OKAY IN THE PHARMACY ONLY. |
|
| 03/23/2018 | MECHANICAL - ABOVE CEILING | Partial Approval | Metal Ducts for Exhaust to the Roof |