Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/10/2018 | ELECTRIC - INTERMEDIATE | Approved | ELECTRIC FINAL 9/07/2018 | |
| 03/15/2018 | ELECTRIC - INTERMEDIATE | Partial Approval | ops walls ok | |
| 03/12/2018 | ELECTRIC - INTERMEDIATE | Not Applicable | NO Access | |
| 02/28/2018 | ELECTRIC - INTERMEDIATE | Partial Approval | dock pits ok | |
| 02/21/2018 | ELECTRIC - INTERMEDIATE | Partial Approval | U.G. conduits at docks ok | |
| 02/12/2018 | ELECTRIC - INTERMEDIATE | Partial Approval | 7- light poles on east side approved | |
| 02/08/2018 | ELECTRIC - INTERMEDIATE | Partial Approval | 1- tilt panel tie in to footer along east wall ok 2-conduit at east/south footer ok to cove 3- ok to 1 side server room |
|
| 01/11/2018 | ELECTRIC - INTERMEDIATE | Partial Approval | UG from bldg to N.W. entry camera ok |