Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
Permit Number - T17CM02821
Inspection Description - BUILDING - PROGRESS
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/23/2018 | BUILDING - PROGRESS | Approved | ||
06/11/2018 | BUILDING - PROGRESS | Not ready for Inspection | restrooms not ADA compliant at shipping office | |
06/08/2018 | BUILDING - PROGRESS | Not ready for Inspection | no work | |
06/06/2018 | BUILDING - PROGRESS | Not ready for Inspection | lavs at admin not ADA compliant flex duct connections to have 2" beaded collars exhaust fans to interlock with time clock support roof drains electrical at conference floor not properly installed |
|
06/06/2018 | BUILDING - PROGRESS | Denied | CLEAR UP ALL OPEN INSPECTIONS NO ONE FOUND ON SITE |
|
05/29/2018 | BUILDING - PROGRESS | Partial Approval | ok TCO warehouse and related restrooms, see building official for temp C.O. docs | |
05/23/2018 | BUILDING - PROGRESS | Not ready for Inspection | cancelled | |
05/22/2018 | BUILDING - PROGRESS | Partial Approval | consultation | |
05/18/2018 | BUILDING - PROGRESS | Not ready for Inspection | ||
05/10/2018 | BUILDING - PROGRESS | Not ready for Inspection | no work | |
05/09/2018 | BUILDING - PROGRESS | Partial Approval | power at pump house ok | |
05/08/2018 | BUILDING - PROGRESS | Not ready for Inspection | complete fire approvals provide sterilization report air balance required at restrooms to be used remove debris from bldg. provide egress lighting provide approval from engineering |
|
02/23/2018 | BUILDING - PROGRESS | Partial Approval | Admin wall clips ok | |
02/08/2018 | BUILDING - PROGRESS | Partial Approval | 1- tilt panel tie in to footer along east wall ok 2-conduit at east/south footer ok to cove 3- ok to 1 side server room |
|
01/26/2018 | BUILDING - PROGRESS | Partial Approval | roof nailing at low roof ok | |
08/18/2017 | BUILDING - PROGRESS | Partial Approval | 4" main at K line ok |