Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/29/2018 | BUILDING - FINAL | Approved | ||
| 09/18/2018 | BUILDING - FINAL | Partial Approval | Pending fore appeoval | |
| 07/24/2018 | BUILDING - FINAL | Partial Approval | PENDING ENGINEERING FINAL OK TO APPLY FOR TEMP C OF O |
|
| 07/20/2018 | BUILDING - FINAL | Not ready for Inspection | pending fire and eng. | |
| 09/06/2017 | BUILDING - FINAL | Partial Approval | PENDING FIRE AND ENGINEERING FINALS PENDING BALANCE REPORT AND METHOD OF STERILIZATION REPORT TO OFFICE BETWEEN 8 AM AND 9:30 AM |
|
| 09/02/2017 | BUILDING - FINAL | Partial Approval | PENDING ALL TRADES PENDING ENGINEERING AND FIRE FINALS AFTER HOURS RECEIVED CHECK #2117 $165.00 |