Permit: T17CM02369

Parcel: 13348128F


Addresses:

100 S HOUGHTON RD

Inspection Status: Approved

Inspection History: BUILDING - PROGRESS

Date Description Inspector Results Comments
10/22/2018 BUILDING - PROGRESS Approved
06/27/2018 BUILDING - PROGRESS Partial Approval SUPERENTENDANT REQUESTS COORECTIVE ACTION NOTICE REQUIRING EXIT RAMP AT REAR NW EXIT BECAUSE OF 10" ELEVATION DIFFERENCE BETWEEN EXIT AND DRIVEWAY
06/06/2018 BUILDING - PROGRESS Partial Approval DW SCREW IN KNEE WALL THEATER 1
06/04/2018 BUILDING - PROGRESS Partial Approval THEATER 1 WING WALL, ELECTRIC, AND DRY WALL 1 SIDE
05/24/2018 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
1- THEATER #2 SHEET ROCK 2ND LAYER NAILING OKAY, PERIMETER WALL OKAY FOR TAPE AND MUD.
2- THEATER #9 KNEE WALL OKAY FOR TAPE & MUD.
05/23/2018 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
1- ELECTRICAL CONDUIT AND BOXES ARE OKAY FOR THEATER #8 IN FLOOR SEATING AREA ONLY.
2- STEEL REINFORCEMENT FOR THE SEATING FLOOR AREA IN THEATER #8 PROVIDED.
05/17/2018 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
1- CONDUIT AND BOXES UNDER THE FOAM FLOOR IN THEATER #7 IS OKAY FOR THE UPPER LEVEL ONLY.
2- SHEET ROCK FOR THE KNEE WALL IN THEATER #8 OKAY FOR TAPE AND MUD.
05/16/2018 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
05/11/2018 BUILDING - PROGRESS Not ready for Inspection IVRS - Inspection :*
05/07/2018 BUILDING - PROGRESS Partial Approval THEATER NO6 ABOVE CEILING OK.
THEATER 3 PRESLAB UPPER TIER OK TO POUR
DRYWALL UPPER MEZZANINE AND SUTH WALL OF LOBBY OK TO TAPE
04/24/2018 BUILDING - PROGRESS Cancelled Arrived at job site and contractor canceled
04/13/2018 BUILDING - PROGRESS Partial Approval
04/05/2018 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
1- SHEET ROCK NAILING IS OKAY FOR THE WEST WALL IN THEATER #5.
04/02/2018 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
1- THEATER #5 NORTH,EAST AND SOUTH WALLS ARE OKAY FOR TAPE AND MUD.
03/26/2018 BUILDING - PROGRESS Not ready for Inspection