| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/14/2017 | BUILDING - FINAL | Approved | APPROVAL PENDING THE ACCEPTANCE OF THE AIR BALANCE REPORT BY BOB SHERRY | |
| 07/12/2017 | BUILDING - FINAL | Partial Approval | AIR BALANCE REPORT SENT TO RECORDS | |
| 07/06/2017 | BUILDING - FINAL | Partial Approval | Approved pending Air bal evaluation, and other open inspetions. | |
| 07/05/2017 | BUILDING - FINAL | Partial Approval | Shell hs not been approved, call for final inspection ofshell. Inspector hs no issues preventing TCO, apply at 201 nStone. Have not seen air balance report. Plumbing changes have not ben addressed. |
|