Permit: T17CM02213

Parcel: 141185930

Inspection Status: Approved

Inspection History: BUILDING - FINAL

Date Description Inspector Results Comments
07/14/2017 BUILDING - FINAL Approved APPROVAL PENDING THE ACCEPTANCE OF THE AIR BALANCE REPORT BY BOB SHERRY
07/12/2017 BUILDING - FINAL Partial Approval AIR BALANCE REPORT SENT TO RECORDS
07/06/2017 BUILDING - FINAL Partial Approval Approved pending Air bal evaluation, and other open inspetions.
07/05/2017 BUILDING - FINAL Partial Approval Shell hs not been approved, call for final inspection ofshell.
Inspector hs no issues preventing TCO, apply at 201 nStone.
Have not seen air balance report.
Plumbing changes have not ben addressed.
06/26/2017 BUILDING - FINAL Not ready for Inspection Need app of shell, air bal, sterilization doc, backflow cert, doc for all changes, dome strainers, air aps, vac relief, cooler drain dn valve as shown, grab bars etc. Complete all work.