Inspection Status: Passed
Inspection History: COT - LCBU - Excavation/Rebar/Zoning
| Date |
Description |
Inspector |
Results |
Comments |
| 10/17/2019 |
COT - LCBU - Excavation/Rebar/Zoning |
TVALENCIA |
Approved |
Entered by DMERANZ1 - |
| 01/31/2019 |
COT - LCBU - Excavation/Rebar/Zoning |
RCAMACHO |
Partial Approval |
Entered by CBELL1 - Eight light pole bases lots one, two, three and 22 |
| 01/30/2019 |
COT - LCBU - Excavation/Rebar/Zoning |
RCAMACHO |
Not ready for Inspection |
Entered by CBELL1 - canceled |
| 08/22/2017 |
COT - LCBU - Excavation/Rebar/Zoning |
RCAMACHO |
Partial Approval |
Entered by RCAMACH1 - LIGHT POLE BASES COMPLETE PENDING AS BUILT FOR ADDED LIGHT POLE |
| 05/10/2017 |
COT - LCBU - Excavation/Rebar/Zoning |
RCAMACHO |
Partial Approval |
Entered by RCAMACH1 - 5 LIGT POLE BASES
SEE HIGHLIGHTD PLAN DATED 2
5/10
PROVIDE RED LINE AS BIIILT TO ASS EXTRA LIGHT POLE BETWEEN LOTS 5 & 7 |
| 05/09/2017 |
COT - LCBU - Excavation/Rebar/Zoning |
RCAMACHO |
Not ready for Inspection |
Entered by RCAMACH1 - CANCELED |
| 05/04/2017 |
COT - LCBU - Excavation/Rebar/Zoning |
RCAMACHO |
Partial Approval |
Entered by RCAMACH1 - SEE HIGHLIGHTED LIGHT POLE BASES ON APPROVED PLAN DATES 5/4 |
| 05/02/2017 |
COT - LCBU - Excavation/Rebar/Zoning |
RCAMACHO |
Partial Approval |
Entered by RCAMACH1 - SEE HIGHLIGHTD LIGHT POLE BASES DATES 5/2 |
| 04/28/2017 |
COT - LCBU - Excavation/Rebar/Zoning |
RCAMACHO |
Not ready for Inspection |
Entered by RCAMACH1 - CANCELED |
| 04/27/2017 |
COT - LCBU - Excavation/Rebar/Zoning |
RCAMACHO |
Partial Approval |
Entered by RCAMACH1 - 6 LIGHT POLE BASES ONLY
SEE HOGHLIGHTED AREAS ON PLAN |
| 04/26/2017 |
COT - LCBU - Excavation/Rebar/Zoning |
mramber1 |
Not ready for Inspection |
Entered by MRAMBER1 - provide minimum 3" clearence from re-bar to earth |