Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 01/17/2019 |
PLUMBING - ROUGH, SOIL |
|
Approved |
Per Matt Ramber level one, two and a portion of five on separate TI permits |
| 08/17/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
DWV and Dom at east stairwell mop sink ok |
| 04/11/2018 |
PLUMBING - ROUGH, SOIL |
|
Not ready for Inspection |
no work |
| 04/04/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
sewer tie in outside bldg ok |
| 04/03/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
sewer tie in within bldg ok |
| 03/23/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
grease receptor venting ok |
| 03/22/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
1st floor main to CL "C" ok to cover |
| 03/15/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
domestic tie in ok |
| 03/14/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
5th level plmg rough ok |
| 03/09/2018 |
PLUMBING - ROUGH, SOIL |
|
Not ready for Inspection |
cancelled |
| 03/08/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
west side grease receptors ok |
| 03/01/2018 |
PLUMBING - ROUGH, SOIL |
|
Not ready for Inspection |
cancelled |
| 02/22/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
ok to cover grease receptors east side to bldg. |
| 02/21/2018 |
PLUMBING - ROUGH, SOIL |
|
Not ready for Inspection |
test failed |
| 02/20/2018 |
PLUMBING - ROUGH, SOIL |
|
Not ready for Inspection |
cancelled |
| 02/16/2018 |
PLUMBING - ROUGH, SOIL |
|
Not ready for Inspection |
cancelled per contractor |
| 02/14/2018 |
PLUMBING - ROUGH, SOIL |
|
Not ready for Inspection |
no work |
| 02/13/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
TRASH AND PUMP ROOM GREASE LINE TO 6' FROM END OF BUILDING NORTH WEST |
| 02/08/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
west grease waste from receptor inlet along west wall approx. 30' ok to back fill |
| 02/07/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
4" waste to grease trap inlet from 90 deg to existing bldg east side ok |