Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
Permit Number - T17CM00673
Inspection Description - BUILDING - PROGRESS
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/17/2019 | BUILDING - PROGRESS | Approved | Per Matt Ramber level one, two and a portion of five on separate TI permits | |
08/13/2018 | BUILDING - PROGRESS | Partial Approval | WALKED ENTIRE JOB ALL 5 FLOORS NO SUPER FOUND ON SITE. SHEETROCK NAILING PUMP HOUSE FIRE WALLS NORTH WALLS OF ELEVATOR 2ND AND 5TH FLOORS ONLY |
|
07/20/2018 | BUILDING - PROGRESS | Not ready for Inspection | ||
07/11/2018 | BUILDING - PROGRESS | Not ready for Inspection | ||
07/10/2018 | BUILDING - PROGRESS | Not ready for Inspection | cancelled | |
07/03/2018 | BUILDING - PROGRESS | Partial Approval | densglas at east exterior stairwell ok | |
05/31/2018 | BUILDING - PROGRESS | Not ready for Inspection | no work | |
05/23/2018 | BUILDING - PROGRESS | Partial Approval | 3rd and 4th level lobby fire alarm conduit not properly installed | |
05/16/2018 | BUILDING - PROGRESS | Not ready for Inspection | sheetrock screws not for structural use | |
05/08/2018 | BUILDING - PROGRESS | Partial Approval | N. stairwell 3 and 4 elec. ok |