Inspection Status: Approved
Inspection History: BUILDING PRE-SLAB
| Date |
Description |
Inspector |
Results |
Comments |
| 01/03/2019 |
BUILDING PRE-SLAB |
|
Approved |
approved per Matt Ramber. 1st, 2nd and portion of 5th floors on separate permits |
| 05/01/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
ok under stairwell |
| 04/23/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
ok at north stairwell |
| 03/06/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
ok trash enclosure |
| 03/05/2018 |
BUILDING PRE-SLAB |
|
Not ready for Inspection |
cancelled |
| 03/01/2018 |
BUILDING PRE-SLAB |
|
Not ready for Inspection |
cancelled |
| 11/22/2017 |
BUILDING PRE-SLAB |
|
Partial Approval |
north and south elevator shafts, south stairway |