Permit: T17CM00673

Parcel: 117121900


Addresses:

40 E CONGRESS ST

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
01/03/2019 EXCAVATION/LAYOUT REBAR & ZON Approved approved per Matt Ramber. 1st, 2nd and portion of 5th floors on separate permits
01/02/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval
12/28/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection canceled
07/26/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection NO SUPER FOUND ON SITE
NO MESSAGE OR NUMBER LEFT FOR CONTACT
07/20/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval south wall 4' footer ok
06/29/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval footer at east end
06/28/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection
06/14/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection no work
06/12/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection no work
05/09/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection no work, another failed inspectio will result in a re fee
05/08/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval east exterior stair footers ok (2)
05/04/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection NO WORK
04/18/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval footers at S.W. site wall ok
04/04/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval north stair footers ok (2
)
01/11/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval pump room deck ok
12/26/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection cancelled
11/22/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval mezz at pump room
11/21/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection cancelled
11/15/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval level 5, shearwalls 1,6,7,8,9 ok
11/09/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 5TH FLOOR SW-3 WALL GRID LINE 8 FROM C TO C.75 AT STAIRWEEL REBAR ONLY
11/09/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval AFTER HOURS PER ARMANDO QUIROZ $165.00 SEE RECEIPT # R1713996
5TH FLOOR SW-3 WALL GRID LINE 8 FROM C TO C.75ONLY
PROVIDE SPECIAL INSPECTION REPORT
11/07/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval level 5 shear walls 4,5 ok
11/01/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 5th level deck ok
10/13/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval south CMU footers ok
10/11/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 4th level ok
10/10/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection contractor cancelled
10/04/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 4th level shear walls 4,5 ok
10/03/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 4th level shearwall 2 and all columns
09/27/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 4th level columns A/1 , A/2 , C/4 , D.7/4
shear walls 6 and 7 ok
09/26/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection cancelled
09/25/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 4th level columns B/1 , B/2 , C/1 , C/2 , C/3 , D/1 , D/2 , shear walls 1,8,9 ok
09/22/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 4th level columns-D/3 , E/1 , E/2 , E/3 , F/1 , F/2 , F/3 , F.5/2 , F.6/1 ok
09/19/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 4th floor slab ok to pour
09/15/2017 EXCAVATION/LAYOUT REBAR & ZON Denied 4TH FLOOR SLAB NOT READY WORK INCOMPLETE.
08/30/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 3rd level shearwall 3 ok
08/29/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection cancelled
08/28/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 3rd level columns A/6 , B/6 , C/6 , D/6 , D/7 , C/7 , B/7 , A/7 , A/8 , B/8 , ok
3rd level shear walls 2,4,5 ok
08/25/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection cancelled
08/24/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 3rd level columns C/4 , D.5/4
3re level shear walls 6 , 7
08/22/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval level 3, shear wall 1,8,9 ok
level 3 columns B/3 , C/3 ok
08/21/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 3rd level columns= A/1 , A/2 , A/3 , B/1 , B/2 , C/1 , C/2 , D/3 , ok
08/16/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 3RD FLOOR PT SLAB
08/15/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
08/14/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection cancelled
08/10/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection cancelled
08/01/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 2nd level shear wall 3 ok
07/31/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 2nd level shear walls 4,5 ok
07/27/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 2nd level shear wall 6 and 7 ok
07/26/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 2nd floor columns- A/7 ok
2nd floor SW 2 ok
07/25/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 2nd floor columns-C/5 , C/4 , D.7/4 , B/7 ok
2nd floor shear walls- 1 , 8 , 9 , ok
07/24/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 2nd floor columns B/1 , E/1 , C/2.2 , C/3 , D/3 , B/3 , A/3 , A/6 , B/6 , A/2 , C/6 , D/6 , D/7 , C/7 , B/8 , A/8 , ok
07/21/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 2nd floor columns- A/1 , B/2.2 , C/1 , D/2.2 , D/1 , D/3 , F/1 , F/2.2 , F/2.8 , F.6/1 , F.5/2.2 ok
07/16/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval LEVEL #2, POST TENSION CABLES AND REBAR IN PLACE - AS PER PLANS. OK TO PLACE CONCRETE. CONCRETE TO RATEDAT 5000psi. FOR ELEVATED SLAB.
07/13/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection P.T. proceeding
07/12/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval walked bottm mat 2nd level
07/06/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GRADE BEAMS AT EAST END RUNNING TO GRADE BEAMS 4 & 5
06/29/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval grade beam on east end
06/28/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
06/21/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval grade beams west end ok pending SK-22 approval
06/20/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection grade beam #4 provide clearence
06/05/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval shearwalls 3,4,5 ok 1st level
06/02/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
06/01/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval column C/2.2 ok 1st level
05/30/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 1-wingwall north elevatoe shear ok
2-both elevator pits ok
3-columns F.5/2.2 , F/2.2 ok 1st level
05/24/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval shear wall 6 ok 1st level
columns B/2 , B/3 , C/2 , D/3 , C/7 , D/7 , D.7/4 , C/6 , B/6 , B/7 ok 1st level
05/24/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval columns A/2 , A/3 , A/6 , 1st level ok
Column F/2 ok per ssk15r with grade beam 1st level
05/23/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval elevator sump pit north elevator ok
columns A/7 , A/8 , B/8 ok 1st level
grade beam 6 ok
SW-1 ok 1st level
05/19/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection WORK INCOMPLETE
05/18/2017 EXCAVATION/LAYOUT REBAR & ZON Cancelled
05/17/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval grade beams 5 & 6 ok
spread footers A/3 , B/3 ok
column D/7 ok 1st level
05/16/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval columns D/1 , D/2 , 1st level ok
grade beams D/3 , d/4 , D/5 and elevator ok
caisson F.5/@.2 ok
05/15/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval revised cage F.5/2.2 ok per SSK15R revision
05/15/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval columns D/1 , E/1 , F/1 , G/1 , E/2 , E/3 , F/3 , ok 1st level
05/12/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
05/11/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection cancelled by contractor
05/10/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection grade beam at elev. 2, provide proper clearence to earth
05/09/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval column base C/2.2 , C/1 , C/3 , C/4 , B/2 , A/2 , B/1 , A/1 , C/5
05/08/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
05/05/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 4 caissons at gl 3/a, 3/b, 4/a, 4/b.
05/04/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval cages B/3 , B/2.4 , A/4 , F.5/2.2 ok
05/03/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval cages C/2.2 , A/1 , A/2 , C/5 , C/1 , B/1 , B/2.2 ok
caissons B/6 , B/5 , A/5 , C/4 , C/3 , C/6 , B/1 , C/1 ok
05/02/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Cages F.5/2.2, B/6, C/6, C/5, C/3, B/2.5, A/5, C/4 ok
Caissons A/7, A/8, B/7, B/8, C/7, D/7, C/8, D/8 ok
05/01/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAISSONS AT GRID LINES E/1, F/1, F/6.1, F.5/2.2, F/2.8, D.7/4, D/5.
05/01/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAGES: A/7, B/7, A/8, C/8, D/8, C/7, D/4, B/8. CAISSONS: D/1, D/2.2, D/3, D/4.8.
04/27/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval caisson inspection on D/3 , D/1 , D/4 , D/4.9 , D/2.2 , E/2.2 , D/6 ok, ok to place in hole
04/26/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval cage inspection ok G.L. F.6/1 , F.5/2.2 , D.7/4 , C/5 , F/1 , F/2.8 , E/1 , E/3 ,
04/20/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GRADE BEAM #4 WEST END 101 FEET NORTH TO SOUTH.