Permit: T17CM00359

Parcel: 110113620

Inspection Status: Approved

Inspection History: REINFORCED MASONRY PRE-GROUT

Date Description Inspector Results Comments
08/04/2017 REINFORCED MASONRY PRE-GROUT Approved OK TO GROUT AND TOP OFF EAST WALL.
08/03/2017 REINFORCED MASONRY PRE-GROUT Partial Approval 1- THEATER EAST WALL 12' - 24' AFFE OKAY FOR GROUT.
08/01/2017 REINFORCED MASONRY PRE-GROUT Partial Approval 1- THEATER EAST WALL FIRST LIFT IS OKAY FOR GROUT.
07/28/2017 REINFORCED MASONRY PRE-GROUT Partial Approval OK TO GROUT WEST WALL TO 24'.
OK TO GROUT THEATER 9 STEM WALLS.
07/27/2017 REINFORCED MASONRY PRE-GROUT Partial Approval OK TO GROUT AND TOP OFF 3 STEM WALLS AT THEATER 7. OK TO POUR SLAB THEATER 7.
07/19/2017 REINFORCED MASONRY PRE-GROUT Partial Approval OK TO GROUT IST 4' LIFT AT WEST WALL, OK TO TOPOFF STEP WALL, OK TO GROUT 1ST 4' LIFT AT 2ND STEP WALL WEST.
06/20/2017 REINFORCED MASONRY PRE-GROUT Partial Approval OK TO GROUT AND TOP OFF EAST AND WEST WALLS EXCEPT AT OPENINGS.
06/13/2017 REINFORCED MASONRY PRE-GROUT Partial Approval OK TO GROUT WEST WALL TO 32' AND EAST WALL TO 28'.
06/09/2017 REINFORCED MASONRY PRE-GROUT Partial Approval OK TO GROUT WEST WALL TO 28' AND EAST WALL TO 24'.
06/08/2017 REINFORCED MASONRY PRE-GROUT Partial Approval OK TO GROUT WEST WALL TO 24' AND WEST WALL TO 20'
06/08/2017 REINFORCED MASONRY PRE-GROUT Not ready for Inspection
06/06/2017 REINFORCED MASONRY PRE-GROUT Partial Approval 1- REINFORCED STEEL IN MASONARY WALL IS OKAY AT 16'-20' FFE 100', LINE A.2/0.6-0.7 AND LINE 0.7/A.2-C, LINE A.7/0.7-1, LINE 0.5/6-G.3, LINE 6.3/05-0.6 AND 0.8-1.
06/05/2017 REINFORCED MASONRY PRE-GROUT Not ready for Inspection
06/02/2017 REINFORCED MASONRY PRE-GROUT Partial Approval 1- REINFORCED STEEL OKAY IN MASONARY WALL AT LINE A.21/0.6-0.7, LINE 0.7/A.2-C, LINE A.7/0.7-1 ONLY.
06/01/2017 REINFORCED MASONRY PRE-GROUT Partial Approval 1- 2ND LIFT AT WEST EXTERIOR WALL AND SOUTH EAST CORNER IS OKAY FOR GROUT.
05/31/2017 REINFORCED MASONRY PRE-GROUT Partial Approval 2nd lift (8') column lines G.3 / 0.5 - G.3 / 1
2nd lift (8') from M.C.J. A.2 / 0.7 - end of interior bearing wall - A.7 / 1. OK to grout.
05/30/2017 REINFORCED MASONRY PRE-GROUT Partial Approval WEST EXTERIOR WALL AND SOUTH EAST EXTERIOR CORNER WALL 1ST LIFT IS OKAY FOR GROUT.
05/23/2017 REINFORCED MASONRY PRE-GROUT Partial Approval OK TO GROUT 1ST LIFT WEST WALL AND SOUTH WALL TO 1ST CORNER.
05/23/2017 REINFORCED MASONRY PRE-GROUT Partial Approval 1- #4 REBAR VERTS PROVIDED.
2-LADDER WIRE PROVIDED.
3- OKAY FOR GROUT AS NOTED ON PLAN.
05/12/2017 REINFORCED MASONRY PRE-GROUT Partial Approval OK TO GROUT NORTH WALL TO 34' AND TOP OFF.
05/11/2017 REINFORCED MASONRY PRE-GROUT Partial Approval OK TO TOP OFF NORTH WALL TO IST CORNER.
05/08/2017 REINFORCED MASONRY PRE-GROUT Partial Approval OK TO GROUT NORTH WALL TO 31'4" PENDING SPECIAL INSPECTION.
05/04/2017 REINFORCED MASONRY PRE-GROUT Partial Approval OK TO GROUT EAST SECTION OF NORTH WALL AND STAIRWELL.
05/02/2017 REINFORCED MASONRY PRE-GROUT Partial Approval OK TO GROUT NORTH WALL TO AROUND CORNER UP TO 28'.
04/28/2017 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
04/26/2017 REINFORCED MASONRY PRE-GROUT Partial Approval OK TO GROUT STAIRWELL TO 20' AND EAST SECTION OF NORTH WALL TO 20'.
04/25/2017 REINFORCED MASONRY PRE-GROUT Partial Approval OK TO GROUT NORTH WALL TO 20'
04/20/2017 REINFORCED MASONRY PRE-GROUT Partial Approval OK TO GROUT NORTH WALL TO 16'.
04/18/2017 REINFORCED MASONRY PRE-GROUT Partial Approval OK TO GROUT NORTH WALL TO 12'.
04/17/2017 REINFORCED MASONRY PRE-GROUT Partial Approval OK TO GROUT NORTH WALL TO 12' TO N.W. CORNER.
04/14/2017 REINFORCED MASONRY PRE-GROUT Partial Approval OK TO GROUT 2ND 4' LIFT AT NORTH WALL.
04/12/2017 REINFORCED MASONRY PRE-GROUT Partial Approval OK TO GROUT 1ST 4' LIFT AT NORTH WALL.
04/10/2017 REINFORCED MASONRY PRE-GROUT Partial Approval