Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/09/2017 | EXCAVATION/LAYOUT REBAR & ZON | Approved | ||
| 07/06/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | OK TO POUR STEM WALL FOOTING AT THEATER 9 STADIUM SEATING. OK TO BACKFILL ELEC. CONDUITS AT SERVICE ENTRANCE. |
|
| 05/17/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | OK TO POUR PERIMETER FOOTINGS, 3 COLUMN FOOTINGS, & INTERIOR MASONRY FOOTING AT FULL HEIGHT WALL. | |
| 03/30/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | OK to pour column lines A.2/0.1 to G.3/0.5 -and- interior footings @ column line C.1 and the next one west -and- the stairwell. |