| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/17/2017 | TDOT-EXCAV GENERAL INSPECTION | Approved | work complete for site work. concrete sidewalk was poured on East side of Colunbus. Pour was declined for pour grade once. The only issue with project is the existing sidewalk on Broadway is out of spec. Contractor claims that someone downtown oked not changing the sidewalk out. Still waiting on conformation. | |
| 04/06/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | No issues with sidewalk on Broadway, new ramps and sidewalk meet speck. all forms and compaction checked. The only issues with Broadway sidewalks is they tied into sidewalks that are out of speck. 2 percent cross slope. curb and sidewalk on Columbus should of been finished today, except grade was not exctable. Concrete was rejected. | |
| 03/07/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | 1/16 and 1/17 area flooded due to rain all work on Broadway complete, two ramps were added and approved. The existing sidewalk is out of spec. I informed the contractor that it needed to be replaced, he said downtown approved it. I am still waiting on a name. |
|
| 01/17/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | no work 1/16/17 and 1/17/17, area was under water due to rain | |
| 01/13/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | 1/11/17 contractor removed existing curb and sidewalk. |