Inspection History Details
Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/27/2016 | TDOT-EXCAV GENERAL INSPECTION | Approved | Area was striped, and job is complete. Small bump over new asphalt, will monitor but Tricon did a good job in a small amount of time to escape disaster | |
| 12/22/2016 | TDOT-EXCAV GENERAL INSPECTION | Continued | Area was backfilled today, no paving due to rain | |
| 12/21/2016 | TDOT-EXCAV GENERAL INSPECTION | Continued | Tricon slurried to spring line, will back fill tomorrow | |
| 12/19/2016 | TDOT-EXCAV GENERAL INSPECTION | Continued | Pipe was strapped with cable today, shot crete scheduled for tomorrow | |
| 12/16/2016 | TDOT-EXCAV GENERAL INSPECTION | Continued | Tricon started to band the water line, but stopped at 12 for there company xmas perty. Tricon will be in on Saturday to shot crete the water line | |
| 12/15/2016 | TDOT-EXCAV GENERAL INSPECTION | Continued | Tricon started work on 12/14/16 with mobilization to the area, and saw cut the asphalt 12/15/16 Tricon built the shoring boxes and started to excavate the pipe. |