Inspection History Details
Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/05/2017 | TDOT-EXCAV GENERAL INSPECTION | Approved | NPL patched Harrison on 1/4 for Southbound and 1/5 for Northbound. No issues, area looks good, needs some small paint replaced | |
| 12/30/2016 | TDOT-EXCAV GENERAL INSPECTION | Continued | 12/29/16 NPL tied in the gas line 12/30/16 NPL slurried backfilled Southbound Harrison. Early day for the long weekend |
|
| 12/27/2016 | TDOT-EXCAV GENERAL INSPECTION | Continued | Tieing over gas line, will slurry hole tomorrow | |
| 12/22/2016 | TDOT-EXCAV GENERAL INSPECTION | Continued | 8 ft hole was dug in South bound harrison, area was plated and shoring added. NPL left early and will not work tomorrow because of Xmas | |
| 12/21/2016 | TDOT-EXCAV GENERAL INSPECTION | Continued | Pipe was pulled trhough bore, Tie in will need a 8x8 hole | |
| 12/19/2016 | TDOT-EXCAV GENERAL INSPECTION | Continued | Potholing Harrison in Southbound lanes. Slow going | |
| 12/16/2016 | TDOT-EXCAV GENERAL INSPECTION | Continued | slow going, only potholing. NPL doesnt want to take a chance with boring conduit on a friday | |
| 12/15/2016 | TDOT-EXCAV GENERAL INSPECTION | Continued | 12/13/16 no work in roadway because contractor couldnt recess steel plates 12/14 and 12/15 potholing Harrison utilitys for upcoming Boring |
|
| 12/12/2016 | TDOT-EXCAV GENERAL INSPECTION | Continued | work started today with potholing and digging a bore pit |