Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 01/03/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
Patch fix will be adressed during Road crossing for primary electric under future permit. |
| 12/12/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Navajo work complete. |
| 12/02/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Work on Navajo for Utility Tap. B Patch due to Inverted water carrying street. |
| 11/30/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Talked to Patrick on-site re.: expired permit. Told him to make sure that permit stayed current until work on Ft. Lowell was complete. |
| 11/23/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Patch Rejected. OK for temp but needs to be milled 2" or replaced. Permit expired. Renewal required before proceeding. |
| 11/17/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
PAG 2 Local Mix not approved for patch in Ft Lowell. Will be plated 1-2 extra days until plants making arterial mix. |
| 11/15/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Site Visit. Fixed one downed VP. Reminded Patrick of Type B patch requirement in Ft Lowell (MS&R) and Navajo (Water Carrying Street). No Ttop Required. Trench over 4' wide. |
| 11/11/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Precon with DirtWorks. Work to start on 11/14 on Ft. Lowell. Trenching on Navajo TBD. |