Inspection Status: Approved

Inspection History: TDOT-EXCAV GENERAL INSPECTION

Date Description Inspector Results Comments
12/19/2016 TDOT-EXCAV GENERAL INSPECTION Approved Perm patch complete. No concerns.
11/18/2016 TDOT-EXCAV GENERAL INSPECTION Continued ASKED TO HAVE VP'S OUT OF BIKE LANE
11/07/2016 TDOT-EXCAV GENERAL INSPECTION Continued Contractor installed app 200' of pipe. Pipe is in place to tie in point and is ready for testing. All compaction tests were acceptable. Cold mix was placed and barricades were down by 0600 per permit requirements.
11/01/2016 TDOT-EXCAV GENERAL INSPECTION Continued Contractor installed app 180' of pipe in center turn lane. All compaction tests were acceptable. Cold patch was placed and all barricades were down by 0600 per permit requirements.
10/31/2016 TDOT-EXCAV GENERAL INSPECTION Continued Janc installed pipe across WB lane and started turn to West. A-Tech tested backfill for compaction and all tests were acceptable. Allowed Janc to start installing backfill in 1' lifts and after several passing tests allowed to test every second lift. Cold patch installed and barricades were removed by 0600 per permit requirements.
10/10/2016 TDOT-EXCAV GENERAL INSPECTION Not ready for Inspection
10/07/2016 TDOT-EXCAV GENERAL INSPECTION Not ready for Inspection