Inspection History Details
Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/12/2016 | TDOT-EXCAV GENERAL INSPECTION | Approved | Final. | |
| 12/08/2016 | TDOT-EXCAV GENERAL INSPECTION | Continued | Slopes on Hedrick ramps and sidewalk check ok. | |
| 12/02/2016 | TDOT-EXCAV GENERAL INSPECTION | Continued | 1.) Met with Dan Robertson and reps from developer and contractor about slope issues at driveway entrances off Campbell & off Hedrick. Campbell driveway will have a slight low spot at the header curb caused by defect in the road allowing for a small section along the gutter to drain inwards in all directions at 1%. To minimize th amount of water that may travel onto the lot, lead inspector is allowing the contractor to pour the concrete driveway 0.5" higher than the header at the area. A 2" COT eclectric conduit that runs along the header on the property side is only about 1" below grade. Removing and replacing the header will damage the line or Campbell or both. 2.) Hedrick St. was determined by phone call to Blanca Espino to not be a collector street, therefore the approach slope for driveway is allowed to not exceed 15% per standard detail. |
|
| 11/18/2016 | TDOT-EXCAV GENERAL INSPECTION | Continued | Checked slope on new 6' SW on West Side of site. All OK. | |
| 11/03/2016 | TDOT-EXCAV GENERAL INSPECTION | Continued | Meeting with McManus, David Stiffey, and Tom Adkins to discuss development standards with regard to ADA requirements. | |
| 09/26/2016 | TDOT-EXCAV GENERAL INSPECTION | Continued | Reminded Superintendant to pull off TC when no longer in use for day. Also to keep grade watered to reduce dust . | |
| 09/21/2016 | TDOT-EXCAV GENERAL INSPECTION | Continued | Precon. DP15-0213. Informed of need to modify permit to include work on Hedrick. Boyd Construction, Trafficade, and McManus Construction were present. |