Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/17/2017 | FIRE SPKLR - FINAL | Approved | ||
| 12/21/2016 | FIRE SPKLR - FINAL | Partial Approval | Phase II South side ONLY. Fire sprinkler drawings FP-2 Column D-A approved. Noted on the Kazal site drawings. Waiting for Phase III for complete final | |
| 12/20/2016 | FIRE SPKLR - FINAL | Partial Approval | canceled | |
| 12/19/2016 | FIRE SPKLR - FINAL | Partial Approval | canceled | |
| 12/17/2016 | FIRE SPKLR - FINAL | Partial Approval | canceled | |
| 12/16/2016 | FIRE SPKLR - FINAL | Partial Approval | canceled | |
| 12/08/2016 | FIRE SPKLR - FINAL | Partial Approval | 1) Some OH approved by CB. See plans. 2) TCO approved for area, columns 4-9 & 9F-11E. |
|
| 10/18/2016 | FIRE SPKLR - FINAL | Partial Approval | This is a partial inspection on a small portion of the OH, see plans. Ok to hard lid this area. |