Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 05/26/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
Final pave completed. No concerns. |
| 05/18/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Ramp checks ok. 4" AC in 2 lifts. Paving today. Subgrade passed compaction. |
| 05/12/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Checked forms on ADA ramp. OK to pour. Sawcut and pave next week. |
| 04/28/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Visited site. Copper Hill has Excavation in ROW. Insufficient traffic control. Told to fix ASAP. CH will call for backfill and concrete form inspections. |