Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
Permit Number - T16EX00477
Inspection Description - TDOT-EXCAV GENERAL INSPECTION
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2016 | TDOT-EXCAV GENERAL INSPECTION | Approved | Strippining only the areas that K E and G effected. Kind of half ass. | |
10/26/2016 | TDOT-EXCAV GENERAL INSPECTION | Approved | K.E and G paved 22nd from colunbus to Alvernon on the west bound lanes on 9/22-9/24. Paving was a nightmare. 561 tons of PAG 11 was used on 9/23/16 and 637 tons of PAG 11 was used on 9/24/16. Paving took forever. Straight edge was used, 8 ton rollers and tickets for asphalt were collected, as well as tack certs. No issues with paving except for the amount of time | |
10/26/2016 | TDOT-EXCAV GENERAL INSPECTION | Approved | the week of 9/26/16 adjustments were performed on west bound 22nd. slow process, all adjustments were done early in the A.M to help alleviate traffic issues | |
10/26/2016 | TDOT-EXCAV GENERAL INSPECTION | Approved | Punch list was given to K.E and G on 10/21/16 it consisted of removing a few driveway aprons, some concrete patching and backfill issues around a fire hydrant. The punch list also consisted of repairing the asphalt patching at the Swann intersection. | |
10/26/2016 | TDOT-EXCAV GENERAL INSPECTION | Approved | Swann intersection milled and repaved on 9/20 and 9/21, punch list | |
10/26/2016 | TDOT-EXCAV GENERAL INSPECTION | Approved | I inherited this job from jose Cazares way after it started, there were alot of issues. irrigation and plants became a issues, which was resolved by santiago and gary whitwer. other issues were time and weather. A few rain days became a issue with backfill. | |
10/26/2016 | TDOT-EXCAV GENERAL INSPECTION | Approved | Job is complete as of Friday the 28 of october, no issues | |
10/26/2016 | TDOT-EXCAV GENERAL INSPECTION | Approved | water inspectors as well as pima county inspectors were on site throughout the project. Numerous eyes on project | |
10/26/2016 | TDOT-EXCAV GENERAL INSPECTION | Approved | Last punch list issue done today. K.E and G replace a collar around a manhole at swann, traffic control will be up tonight to protect the area, Job is OFFICALLY finished |