Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/22/2016 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
| 12/20/2016 | PLUMBING - ROUGH, SOIL | Denied | 1- SHALL PROVIDE A SEPERATE 2" DRAIN FOR THE LAVATORY IN THE POWDER ROOM. 2- PROVIDE A WATER TEST ON THE SYSTEM. |
|
| 12/12/2016 | PLUMBING - ROUGH, SOIL | Partial Approval | 1- DWV WATER TEST PROVIDED. 2- THIS INSPECTION IS FOR THE UNDERSLAB ROUGH PLUMBING EXCEPT THE POWDER ROOM. 3- OKAY TO BACKFILL TRENCH EXCEPT AT POWDER ROOM. |
|
| 12/09/2016 | PLUMBING - ROUGH, SOIL | Denied | 1- DWV WATER TEST FOR THE WEST SIDE ROUGH PLUMBING WAS DOWN. 2- THE TRAP ARM FOR THE MASTER BEDROOM TUB REQUIRES A MINIMUM OF TWO TIMES THE PIPE DIAMETER TO AVOID HAVING A S TRAP. 3- SHALL CONNECT THE 2" WASTE LINE FOR THE WASHER BOX DOWNSTREAM OF THE WATER CLOSET. 4- RE TEST THE SYSTEM. |